Home
| Databases
| WorldLII
| Search
| Feedback
High Court of Solomon Islands |
HIGH COURT OF SOLOMON ISLANDS
Civil Case No: 144 of 1996
ISLAND CONSTRUCTION MAON MANAGEMENT LIMITED
v
AIR TRANSPORT LIMITED
<
High Court of Solomon Islands
(Palmer J.)
Civil Case No.: 1o.: 144 of 1996
Hearing: 30th July, 1998
Judgment: 3rd February, 1999
A. Radclyffe for the Plaintiff
Sol-Law for tfendantlass="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> PALMER J.: Island Construction Management Limited (the �Plaintiff�) is a company engaged in sawmilling and logging. In early 1995 it entered into a sub-contract with Mubu Sawmilling (a firm), to extract logs for mill processing or export.
Mubu Saing (the Licensee) held a valid Milling Licence No. Tim >Tim 3/173 (see Exhibits 14 and 15). This is not in dispute. This entitled the Licencee to mill timber from logs felled within the area specified in the Licence (see Clause 2 of the Licence). A footnote in the Licence [see page 2, para. (iii)] authorised the Licensee to export a quota of 20,000 m3 of logs per year.
The Plaintiff�s ation under the sub-contract was to fell and extract logs and transport them to the Mill site for processing and or export.
The Defendant on the other hand runs a helicopter serwhich included providroviding hire of heavy helicopters for haulage of logs in the logging industry (see Exhibit 43).
THE TIMBER MILL LICENCE:
A number of points to be noted about the Milling Licence. It was issued on 9th February 1994 for one year and renewed again for another year on 9th February 1995. In April 1994, this Court ruled in Forest & Another v. Mahlon Ali & Attorney-General, Civil Case No. 1/94, judgment delivered 12 April 1994, that it was unlawful for the holder of a Milling Licence to fell trees and remove them for milling without a valid timber rights agreement. The footnote therefore which sought to authorise the export of logs under the said licence became invalid if not from 12 April 1994, with effect from the date the orders of the Court in Forest�s Case became known. Towards the end of 1994 (8 months later), it should have been common knowledge in the logging industry, that the footnote for what it was worth, was invalid without a timber rights agreement duly approved by the Minister. If not, by the time the Milling Licence became due for renewal on 2nd February 1995, [some ten (10) months later] there would have been no basis in law whatsoever, for the inclusion of paragraph (111) of the said footnote.
The Commissioner of Forests had been a party to the Forest & Ano; Another v. Mahlon Ali Case (ibid) and therefore would have known (ignorance is no defence to the law) that unless a timber rights agreement exists for the felling and removal of trees, a milling licence did not authorise the same. In view of his responsibility in policing the Timber and Forest legislation, he would have been one of the first persons to have known about this decision and its effect on the milling licences issued. Unfortunately the manner in which this has been dealt with has been quite disappointing; if not bordering on carelessness. The inclusion of paragraph (iii) to the footnote in the said Milling Licence of Mubu Sawmilling for instance, should never have been done, especially at the time the licence came for renewal. This with respect could only have caused confusion to the Licence holder.
<
EVENTS LEADING TO THE SIGNING OF THE AGREEMENT BETWEEN THE PARTIPARTIES:
In May 1995, the Managing Director of the Plaintiff Company, Mr. Lennea entered into negotiations with the Managing Director of the Defendant, Mr. Grouse, for possible hire of a heavy helicopter to lift logs at Mono from the stump to the log pond or camp. This was to be done pursuant to the sub-contract the Plaintiff had entered into with Mubu Sawmilling. The Plaintiff relied on Mubu�s Milling Licence in turn for the milling and export of the logs. It is also pertinent to note that Lennea assumed that whilst Mubu Sawmilling did not have a felling licence it was still alright for the landowners themselves to fell their own logs and supply them to the mill for processing or for export.
On 4th May 1995, Lennea wro the Defendant and expresspressed his intentions as follows:
�Dear Sir,
se accept this letter as a follow up to our discussions tods today regarding (sic) our request to enter into negotiations with yourselves for the helicopter extraction of logs for our operation in Mono Western Province and other locations through out the Solomons where ICM is involved in lumber milling.
We request a contract price per cubic meter from the stump to p to the dump point.
Also give us a realistic time frame, accommodation requirements, minimum guarantee requirement terms of payment etc. �[See Exhibit �2�]
Grouse responded by letter dated 15th May, 1995 outl outlining his requirements (see Exhibit �3�). At paragraph 2 of his letter he pointed out that both of their Ka 32 helicopters would not be available until about early July. He also pointed out in paragraphs 3 and 4 that it would take about six weeks after receipt of initial payment under the terms of the Agreement before the Helicopter could begin operations on site. It would first have to be brought over to Honiara before it could be delivered to the Plaintiff to commence operations at Mono. I quote in full the relevant paragraphs as this is important in understanding the time frame in which the Helicopter was expected to be made available for delivery on site in Honiara.
�The PNG programme, since the time of writing, has been bron brought forward and both our available Ka 32�s are now under contract until early July. It is a little unfortunate that our negotiations could not have been concluded earlier however the longest lead time task is the placement of the supply of helicopter fuel, fabrication of the fuel tank farm and its shipment to site.
As helicopter fuel is the responsibinsibility of this company, together with consequent contractual obligations to the fuel supplier for a schedule of payment, we are unable to execute the fuel contract until the Head Agreement between ourselves is executed and the initial payment satisfied. The fuel company states that 4 -5 weeks will be required for the fabrication of the tanks and reticulation pipe work and a further 7-10 days for shipment from PNG to site. The company tanker must also be scheduled correctly for the first unloading of fuel into the installation, this has been tied in with your requirements for the delivery of diesel fuel by the same vessel. Different seaside manifolds and pipework for diesel and Jet A1 are necessary, adding time for fabrication, however the cost of diesel delivered in this manner is greatly reduced.
The fuel installation is expected to be in servicervice at the same time as the helicopter will be available thus enabling production to begin about six weeks from the receipt of initial payment under the terms of the Agreement, contingent upon the fuel supplier meeting the fuel installation delivery and certificate schedule.� (Emphasis added)
The time frame indicated in the letter and reflected in the athe agreement subsequently signed between the parties, was about six weeks for the Helicopter to be brought over and delivered at Honiara from Papua New Guinea. The agreement executed on 16 May 1995, (Exhibit �I� and hereinafter referred to as �the Agreement�) reflected that time frame.
TERMS OF THE AGREEMENT:
The Plaintiff seeks to rely on the terms of the Agreement. The Agreement in essence required the provision of a Ka 32 helicopter (hereinafter called �the Helicopter�), for the haulage of logs primarily at Mono, but there is provision for the helicopter to be used at other locations throughout Solomon Islands where the Company might also be involved in timber milling. See Clause 3(c), of the Agreement which states as follows:
�During the term os agreement the Charterer mrer may position the helicopter to any of its work sites within Solomon Islands and bear the costs of such positioning.�
This is consistent with was stated in the letter of 4th May, 1995 1995 (Exhibit �2�). Clause 2 of the Agreement refers to the date of commencement and termination:
�The hiring created by this agreement shall commence on thon the 15th day of July 1995 and shall terminate one year later. Provided that both parties agree, an extension of this hiring may be undertaken by the Charter giving written notice to the Company three months prior to the termination date of this agreement.�
[Emphasis added]
It is importantear in mind that the date fixed for commencement of h hiring on 15th July 1995 took into account the time period of about six weeks indicated in the letter of 15th May 1995 (Exhibit �3�), when the helicopter would be made available; that, provided the initial payment of USD37,000.00 stipulated under Clause 12(b) was paid within seven days of signing, the Helicopter should be ready for delivery in Honiara on or about 15th July, 1995. Unfortunately, there was a delay in the payment of that initial sum. Instead of payment being made within 7 days after signing, it was paid on or about 7th July 1995, some six weeks after the due date.
EFFECT OF DELAYED PAYMENT:
Clause 12(b) of the Agreement not only required the paymenthe sum of USD37,000.0000.00 within seven days of signing, it also made the Agreement conditional upon payment of the said sum. This meant the Agreement was dependent upon payment of the said sum. That is, its existence or enforcement depended upon the payment of the said sum within the stipulated time period. Non-payment of the said sum within the stipulated time period amounted therefore to a breach of an essential term of the contract and which entitled the Defendant to treat the breach as a repudiation which discharged it from further performance of the Agreement and to sue for damages.
class="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> The evidence however as adduced did not su in any way that the Defendant sought to exercise its right to have the Agreement terminated for the breach. Rather it showed conclusively that the Defendant affirmed the contract by commencing action to have the helicopter ready for shipment and delivery to Honiara.
ass="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> There was ho a vital time factor which affected the Agreement. It was was subjected to delay. By delaying payment, the time period within which the helicopter would be delivered was also subjected to delay. According to the unchallenged evidence of Grouse, mobilisation of the helicopter for delivery commenced only after payment had been received on or about 14th July 1995. Note payment was made on 7th July 1995. This meant clause 2 of the Agreement couldn�t be compiled with in the circumstances; that is for hiring to commence by 15th July 1995. It has not been challenged in evidence that the particular helicopter identified for the purpose was located at the said time in Singapore. Also that it would take time for Grouse to sort out crews that were available and qualified and to make other necessary payments towards their pay and other charges. During this time, he had gone to PNG to have all these matters sorted out. By 18th July 1995, (11 days after payment of the mobilisation charges) the Helicopter was positioned in Papua New Guinea ready to be shipped to Solomon Islands.
respectful view the answer must be no. The date of commencmmencement of hiring fixed for 15th July 1995 must be viewed within the context of the whole Agreement, in particular Clause 12(b). It had been envisaged that the payment of USD37,000.00, would go towards assisting the Defendant on its mobilisation costs for delivery of the helicopter in Honiara, but that this would be refundable. The date of commencement accordingly had been fixed to take into account that mobilisation period and when the helicopter would be made available in Honiara, assuming that payment was made on time. The last date for payment of the said sum was 23rd May 1995. Had payment been made on time, there would have been more than sufficient time available for the helicopter to be prepared and made ready for delivery at Honiara. This is entirely consistent with what had been previously stated in the correspondences between the parties.
<
The Plaintiff therefore knew that the helicopter would have to be transported from PNG and that it would take some 6-8 weeks before it could be delivered in Honiara. The terms of the contract had been so worded to take that time period into account. By delaying payment, the date of commencement was subjected to further delay. So even if the Plaintiff were to insist on performance of the contract by that date, it would have been physically impossible for the Defendant to comply.
THE LEGAL EFFECT:
In my respectful view what actuaook place was a variation; ion; instead of a breach. The date of commencement was varied by consent of the parties. If not it is to be implied in the Agreement by the conduct of the parties.
class="Mss="MsoNormal" style="margin-top: 1; margin-bottom: 1"> THE EVENTS AFTER 15TH JULY 1995:
t happened thereafter? The Agreement having been varied by d by the consent of the parties so that commencement date was now deferred, it is not in dispute Grouse proceeded to mobilise the helicopter and by 18th July 1995, it had been brought over to Papua New Guinea (�PNG�) ready for shipment to Honiara. What happened thereafter is crucial to this case. On the same date, an order was obtained from the High Court by the Plaintiffs, John Havea and Ivan Maike in Civil Case No. 178/95 against inter alia, Mr. Lennea, (the Sixth Defendant), restraining him from entering Mono or Stirling Islands to carry on the felling, extraction or sawmilling of any timber (see Exhibit �4�). On or about the same day, word somehow reached Grouse in PNG about that injunction. This news had a drastic effect on the preparations and arrangements for shipment undertaken by Grouse. In evidence, it was made abundantly clear to this Court that he was not prepared to allow the helicopter to be used in operations which were unlawful and not in compliance with the laws of this country. Grouse viewed the imposition of the injunction with graveness; that to proceed with the Agreement at that point of time could result in him participating in some unlawful activity in Solomon Islands.
THE 1995 DIARY BOOK OF GROUSE:
Exhibit �31� is the 1995 Diary Book of Grouse. It contains the recorrecords and notes of daily events which Grouse habitually enters into his diary, if not at the same time, in the evening of each day. At the entry for 18th July 1995, the following was recorded:
�Ian Robertson called re my fax higx highly pissed off at contents especially Prok Bank Guarantee status. I said that my news was current and that the injunction with it would be served shortly.�
This entry was consistent with the fact that an injunction had been obtained from the Court on the same date. In the entry for 20th July 1995, he recorded the following:
lass="MsoNoMsoNormal" style="margin-left: 36.0pt; margin-top: 1; margin-bottom: 1"> �Received copy of injunction on Kalu from Len - sent copy to Ian Robertson.�
Again this is consistent the fact that it would have taken a couple of days fays for copies of the orders to be made available. What happened thereafter was crucial. On one hand we have the Defendant mobilising his helicopter ready to be shipped over from PNG on or about the same date, whilst on the other hand, the operations intended to be undertaken at Mono were subject to restraining orders from the Court. Lennea was the Sixth Respondent named in that injunction and therefore directly affected by the order.
ass="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> THE EFFECT OF THE ORDER: p class="MsoNormal" style="yle="margin-top: 1; margin-bottom: 1"> p class="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> It is important to appreciate the legal effect of that order on the Plaintiff. I quote in full, paragraphs (1) and (2) of the Order.
�1. The Defendants their servants or agents be restrained from enom entering Mono or Stirling Islands to carry on the felling, extraction or sawmilling of any timber or an action in any preparation for the same save and except the attendance at a valid timber rights meeting of the Famoa Area Council until trial or further order.
2. The sale proceeds of any t already felled, extracted cted or milled prior to the service of this order upon the First Defendant, or Second Defendant, or the Third Defendant, or the Sixth Defendant; shall be paid into Court or into an interest bearing account in the name of the Plaintiff's Solicitor forthwith.�
Thd order can be described as a blanket restraining order; prr; preventing inter alia, the Sixth Defendant (Lennea) from entering the operation zone. This meant even if the helicopter had been brought over to Honiara and even if Lennea might have thought otherwise, it still could not be used at Mono by virtue of the injunction. To do otherwise would place Lennea, his servants or agents in contempt of the Court Order.
This order was in place until 12 September 1995 when it was varied to enable trees already felled to be removed and sold.
Lennea must be deeo have knowledge of the injunction from the date it w was served on him; most likely a couple of days after. That injunction is crucial to the proposed operations at Mono because its effect is direct. Lennea had two alternatives open to him. He could insist on bringing the helicopter over to Solomon Islands and using it elsewhere, or to consent that it remain in PNG until the issue on injunction be sorted out.
insist on bringing the helicopter to Mono would be tantamontamount to contempt of Court. That he could not do even if he might have thought otherwise. To bring the helicopter into Solomon Islands in any event meant it would have to be deployed elsewhere. Unfortunately, there is no evidence to suggest that this intention was expressly conveyed to Grouse in PNG and that any such request or instruction was given. The only evidence on this from Lennea pertained to his denial in examination in chief that he consented to the helicopter being detained in PNG. I quote:
�Q. Around that time in July when you heard about the Court Order did you discuss the matter with Mr. Grouse?
A. I believe we did, I thiI think with Lenny Palmer. Mr. Grouse was in PNG that time I believe. I don�t know how much discussions we had.�
�Q. Did you tell them that you noou no longer required helicopter in Solomon Islands?
A. No, because we had spent a lot of money and tried to sort out legal problems in there. So we definitely needed the helicopter.�
ass="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> There was mention of an alternative location at Enoghae but the evidence adduced showed that a helicopter was not needed until about July 1996 (about a year later). No other location was specifically mentioned as available during the said period. It is clear on the evidence therefore that the focus was on the operations at Mono; nothing about use elsewhere. On the question therefore whether there is evidence to suggest that the Plaintiff insisted on having the helicopter brought over to Solomon Islands for use elsewhere other than Mono, the answer must be no.
p class="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> Under cross examination, Mr. Lennea conca number of crucial points.ints. I quote:
ass="MsoNoMsoNormal" style="margin-left: 36.0pt; margin-top: 1; margin-bottom: 1"> �Q. You knew that ATL was not prepared to brin bring in the helicopter in breach of the injunction?
A. Yes.
Q. You accepted that in truth?
A. Yes.
Q. You accepted that it couldn't come because you would sort out the legality?
A. Yes.�
ass="Mss="MsoNormal" style="margin-top: 1; margin-bottom: 1"> Lennea thereknew that Grouse was not prepared to bring in the hel helicopter in view of the injunction. In spite of this, he did not give specific instructions as to what alternative arrangements or sites he had in mind in Solomon Islands for the helicopter to be used if brought into the country in any event. He also did not raise any direct objections about the decision to redeploy in PNG. Nor did he seek to treat the redeployment as a repudiation of an essential term in the Agreement and thereby entitling him to have the Agreement terminated and sue for damages. Instead his actions point more to an affirmation of that crucial decision to redeploy.
PROK BANK:
p class="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> Ian Robertson was the recognised represeve of Prok Bank. Prok Bank Bank played a crucial role in the logging operations of the Plaintiff. In examination in chief, Lennea conceded Prok Bank was a partner in their business operations and acted as financier and manager of the operations. They had invested substantial sums of money in the operations of the Plaintiff and so a lot was at stake. This would have entitled them in the least, to have some, if not, a lot of say in how things were to be done at any rate. Also as financier and manager of the operations of the Plaintiff, they were as interested in ensuring that whatever was undertaken was successful, with costs minimised as much as possible.
From clear and undisputed evidence before this Court, the amount of USD37USD37,000.00 was funded by Prok Bank. The delay in payment was due partly to the delay in having Prok Bank process the funds for payment. This is evident from the numerous conversations recorded in the diary of Grouse concerning arrangements for payment by Prok Bank (see entries in the 1995 Diary for 31st May, 6th June, 13th June, 19th June, 3rd July).
class="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> I accept therefore the submission that Prnk stood in the position ofon of agent of the Plaintiff
THE DECISION TO REDEPLOY THE HELICOPTER IN PNG:<
<
Thesion to redeploy appears to be the most logical, obvious anus and reasonable thing to do in the circumstances. I find on the balance of probabilities the Plaintiff had consented to the helicopter being redeployed in PNG whilst he tried to sort out its legality.
But even if it could still beed otherwise (which is not not feasible on the evidence), that the helicopter should have been brought to Solomon Islands at any rate, it is clear on evidence, Ian Robertson of Prok Bank had consented to the helicopter being redeployed in PNG to help alleviate further costs to the Defendant.
lass="MsoNoMsoNormal" style="margin-left: 36.0pt; margin-top: 1; margin-bottom: 1"> �I spoke to Robertson. He was surprised aboutabout the injunction because he was under the impression that everything was fine. I said it was undesirable to send equipment. So decision was made to clarify the matter. We were in the situation where under the terms of our contract, as Lessees of the helicopter, we were committed to pay minimum charges. So it was a matter of financial survival that we find some alternative equipment,��
(Page 44 of transcript)
At page 45 he continued -
�I didn�t discuss it with Lennea but in t in discussions with Robertson, I told him (that is, about the redeployment of the helicopter). He agreed with me because saw no other option.�
This has been virtually unchallenged.
It is clear on evidence therefore, the decision to redeploy was made by G Grouse in consultation with Ian Robertson of Prok Bank and with the knowledge of Lennea. It was taken as a response to the unfortunate turn of events surrounding the operations on Mono Island; basically a sound and wise decision to avoid unnecessary losses to the parties. Further it was an accepted fact that the Defendant had incurred expenses when arranging to have the helicopter transported from Singapore to PNG in preparation for further shipment to Honiara for delivery to the Plaintiff. It was therefore a somewhat important decision for the Defendant that redeployment was seriously considered in the circumstances. In his evidence before this Court, Grouse states the decision was made a couple of days later.
One of the issues which has been raised in relation to the decision to redeploy is whether it amounted to a breach. In weighing and balancing all the evidence before me, I am not satisfied the action of the Defendant in redeploying the helicopter in PNG was in breach of the Agreement. It was made, if not with the consent of Lennea, with his knowledge and with the authority of Ian Robertson of Prok Bank. Bearing in mind that Prok Bank was a partner in the business operations of the Plaintiff, I am satisfied the actions of Ian Robertson can be construed as amounting to that of an agent and done on behalf of the Plaintiff and therefore binding.
The injunction therefore had a further drastic effect on the commencement of hiring of the helicopter. The date of commencement of hiring was further subject to delay whilst Lennea sought to have the legal issues sorted out. The legal effect of this is crucial to understand. In my respectful view, there was a further variation of the Agreement. The date of commencement was further deferred.
THE ALTERNATIVE ARRANGEMENTS OF THE DEFENDANT:
lass="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> In redeploying the helicopter in PNG the Defendant hired out its helicopteropter initially to Clayfield Pty. Ltd. for a period of 3 months and thereafter to Barracuda Pty. Limited. (See Exhibits �35�, �36� and �37�)
p class="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> RE-MOBILISATION:
ass="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> On 12 September 1995, the Order imposed on 18th July 1995 was s varied to enable trees already felled to be removed. This meant Lennea could now enter Mono but only to have the trees already felled removed, not to fell any more trees. Any suggestions therefore that he could fell new trees is without basis, although it appears he did make an attempt to get a felling licence but was refused by the Commissioner of Forests.
The decision to remobilise however appears only to have been made some two months later. On 23rd November 1995, Grouse was asked by Lennea to remobilise with a view to commence loading on 14 December 1995. This was made after a buyer had been secured by Lennea (see Exhibit 16).
THE KAMOV 32 HELICOPTER:
One of the issues raised intion to this is whether this failure to provide a hela helicopter when required, amounted to a breach on the part of the Defendant? The Plaintiff had submitted this was a breach. Unfortunately I must disagree.
The Kamov 32 helicopter had been redeployed in PNG with the consent of the Plaintiff. This I had found on the evidence before me. Lennea thus knew the helicopter would be hired out to other users. The legal consequence of this is that it became subject to contractual obligations to third parties (Barracuda), so that if any decision was taken for remobilisation it would be subject to a release from the Barracuda contract. This was the problem facing Grouse. Despite attempts by him to have the helicopter released early, Barracuda was unwilling to do so. It wasn�t thus the case where the Defendant was unwilling to provide the helicopter. He was willing and wanted to, but couldn�t in the light of commitments he had entered into. The only time he could comply was when the Barracuda contract expired on or about 16th January 1996. Unfortunately it became apparent that even after expiry of the Barracuda contract, the helicopter could not be made available immediately as it would have been subject to service, including an engine change. The earliest the helicopter therefore would have been available would have been towards the end of January 1996.
class="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> The problem unfortunately was Compounded b commitment made by Lennea nnea to have a shipment of logs dispatched by end of December 1995 and arranging shipping for that time when it had not been confirmed that the helicopter was available for that time.
In my respectful view the inability of the Defendant to make available a helicopter when requested, did not amount to a breach of the Agreement. It wasn�t the case where the Defendant was unwilling to comply with his obligations. It was willing but unable to, due to circumstances beyond its control, the helicopter simply could not be made available within the time period required. It was subject to release by a third party and further subject to an engine change which would cause further delay.
But even if it might be argued that there had been a breach I find the Plaintiff had had waived his rights by agreeing to enter into a new or alternative arrangement for the use of a Skycrane helicopter to lift kwila.
EXHIBIT 16:
ibit 16 is the copy of the purchase order placed by Pacificcific Ocean Timber Company Limited (the �Buyer�) for kwila logs (latin name �Intsia Bijuga�). Pacific Ocean Timber Company was the company with whom Lennea had entered into an agreement with for the sale of logs that had been felled at Mono. The purchase order was dated 21st November 1995 and sets out in detail the order of the Buyer. The quantity of logs required per year was 100,000 m3. The length of the logs were to be between 6 - 12 metres but may be reduced to 4 metres in length if in excess of 5 tons in weight. It also required that the first shipment of 5,000 m3 be made by end of December 1995.
class="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> There is an interesting point that should be noted. According to a break down of species recorded by Moses Aopuru (an employee of ICM) dated 28th November 1995, the total volume of kwila cut and in place was only about 74.60 m3 though I accept there were other logs still out in the bush. This was estimated to be around 1,600 m3 by Lennea. This however is still well below the amount of 5,000 m3 required by the Buyer in its first shipment. Bearing in mind the variation did not permit the felling of fresh logs, it would seem virtually unlikely that the order of 5,000 m3 for kwila logs would ever be met.
SKYCRANE NOVATION/VARIATION:
It is relevant to note that the decision to remobilise made on or about 23rd November 1995 related directly to the order placed in Exhibit 16, for the haulage of kwila logs. This had a direct bearing on the decision to remobilise. Whilst on one hand there were attempts to try and get an early release for the Kamov 32 helicopter, Grouse was of the view that a larger helicopter in any event would be required for the lifting of kwila logs, as this had a greater density of 1:4, more than the lifting capacity of the Kamov 32 helicopter for logs of similar size with a density of 1:2:1. A subsequent test carried out on a sample confirmed the density to be at 1:35. It was thus eventually agreed that a larger helicopter would be required. But even if it might be argued otherwise, Grouse was adamant a larger helicopter was required.
Thbsequently set in motion negotiations for a different helichelicopter to be used other than the one mentioned in the Agreement. Following discussions, it was agreed Grouse would try and negotiate with Erickson for a larger Skycrane helicopter. It was however obvious from the beginning the whole arrangement for hire of a Skycrane helicopter ultimately depended on the terms set by and approval of Erickson. If Erickson did not agree no skycrane helicopter would be made available.
THE ERICKSON DEAL:
Part of the requirements imposed by Erickson included the payment upfront of mobilisation and fuel costs to be funded by a red clause advance on the buyer�s letter of credit. This included the initial payment of USD80,000.00 towards helicopter fuel and transportation costs on 27th December 1995, with a further sum of SBD153,499.13 paid on 9th January 1996. Also on 27th December 1995, the sum of USD250,000.00 was paid towards �mobilisation payment and part payment for the transport of 6,500m3 of logs forming the first shipment� (see Exhibit �8�).
Unfortunately, in sof these substantial payments, it appears Erickson wa was never fully satisfied. It gave no approval for the release of its Skycrane helicopter. The proposed arrangement consequently fell through and had to be abandoned. By 8 January 1996, the Erickson arrangements were shelved. The legal issue which Mr. Sullivan raises in respect of this arrangement is whether there had been a novation or variation of the original agreement?
p class="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> NOVATION:
The essence of �nov� is the rescission or extinguishment of a contract a and the substitution or replacement by a new one on new terms between the same parties, or same terms but with a third party added (Ansons Law of Contract 25th Edition, page 442; see also Chitty on Contracts 26th Edition paragraph 1436). That can hardly be said to be true in this case. The original contract was not extinguished and replaced by a new one, nor the parties changed.
lass="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> VARIATION:
class="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> RE-ACTIVATION OF THE ORIGINAL AGREEMENT:
With the demise of the Erickson deal, the original agreement was reactivated or reverted to again for the supply of a Kamov 32 helicopter. Unfortunately the same problem which affected its earlier release remained, Grouse could not get an early release from Barracuda Pty. Limited. A number of meetings were convened to try and get things sorted out. One of these occurred on 8 January 1996 in the Office of Misi & Associates. Present at that meeting were representatives of ICM, Lennea and Mrs. Lennea; a representative of Prok Bank, Victor Shumilo; representatives of the Buyers, Phillip & Johnny Ng; and representatives of ATL, Grouse and Mark Stafford. Records of copies of the minutes of that meeting are contained in Exhibit �40�. The contents revealed what was discussed and the state of things at that point of time. By then (8 January 1996) the Erickson deal was definitely out. Discussions were more focused on reviving the original agreement, in view of the shipping arrangements that had been made and potential demurrage charges if the ship was delayed and returned dead freight.
One of the crucial items discussed was the availability of the Kamov 32 hel helicopter. After pointing out that getting an engine change was delayed over the Christmas/New Year period, Grouse gave a �best estimate� for the positioning of the Kamov 32 at Mono for �Friday pm�. Presumably this meant Friday next. Following that meeting, Grouse and Victor Shumilo left for PNG on Wednesday 10th January. They were supposed to bring back the helicopter on Friday 12th January 1996. Lennea also left for Mono at the same time to prepare for the arrival of the helicopter and shipment of logs. This included making arrangements for the purchase of fuel and transportation to Mono. In this regard 320 drums of Jet Al fuel were purchased and shipped to Mono via Markwarth Shipping Company (see Exhibits �11� and �12�).
The unchallenged evidence of Grouse as to whatened at PNG is crucial. . His attempts to get an early release were again unsuccessful due it seems to the fact that Barracuda was in the middle of an oil well rig. That meant the Kamov 32 was no longer immediately available for positioning in Honiara. Further it was pointed out in evidence by Grouse that by the time it was released from its contractual obligation with Barracuda it still had to undergo an engine change and would only be available by the end of January 1996. It is important therefore to understand that as far as the Agreement regarding the supply of a Kamov 32 helicopter is concerned, the date for commencement of hire was further delayed to the end of January 1996. I have already dealt with the question whether such delay amounted to a breach of the Agreement and therefore do not need to repeat what has been said. This delay did not amount to any breach.
re was then it appears an attempt by Grouse to have the Agre Agreement varied at this point to meet the urgent need of the Plaintiff for a helicopter; bearing in mind that there were shipping commitments that had been entered into by Lennea and so the provision of a helicopter immediately was paramount at that time. The suggestion for a variation came about through the offer of Victor Shumilo, representative of Prok Bank. He had offered through contacts he had in Ladivostoch to try and arrange for a helicopter to be hired from a company there. The new arrangement would be for the Plaintiff to deal directly with that company but to operate in Solomon Islands using the licence of the Defendant for a flat rate fee at 20%. This was subsequently communicated to Lennea and according to the evidence of Grouse, accepted by him. Arrangements were then commenced for the helicopter to be mobilised and brought over. According to Grouse, arrangements for a crew to come through were commenced on 12 January 1996. On 13 January 1996 he waited for word to come through regarding the final crew and a long line for the helicopter. These appear to be the final arrangements before word came through shortly after, that the operation at Mono had been abandoned. On 15th January 1996, he was told that Mono had been abandoned.
What happened was that the blanketraining order was re-imposimposed on 15th January 1996. This is not in dispute. That apparently dealt the final blow to the Mono operation despite the view of Lennea that the Mono operations were abandoned due to the unavailability of a helicopter. It is partly true the Kamov 32 helicopter was not available immediately, but that did not mean the Defendant was in breach. I have already ruled on this. The helicopter would be available but only towards the end of January 1996.
The real reason therefore for the abannt of the Mono operations wons was the re-imposition of the blanket restraining order, because even if a helicopter was made available immediately through the new arrangements undertaken, it could not possibly be used at Mono. As for any suggestions that the helicopter could be used elsewhere, there is little evidence in support.
FRAUDULENT REPRESENTATION:
The Defendant alleges as part of its defence that Lennea had made a frauduleudulent representation regarding the availability of a valid timber license covering Mono Island and permitting the export of round logs.
The law on fraudulent misrepresentation has been firmly established in the case of Derry v. Peek (1889) 14 Asp. Cos. 337. At page 374 Lord Herschell sets out in a nutshell the elements of fraudulent representation. I quote:
�frs proved when it is shown town that a false representation has been made-
(1) knowingly, or
(2) without belief in its truth, or
(3) recklessly, careless whether it be true or false�.
p class="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> The falsresentation alleged was that Lennea claimed he had all necessary licences and permits for log exports. Mr. Sullivan submits Lennea must have known that his representation was false. He relied on the fact that:
(1) Lennea admits ICM had no licences or permits itself, and
(2) that in spite of what was said about the Milling Licence of Mubu Sawmilling it had no valid licence to fell and export timber.
It is not in dispute ICM had no timber licence to fell and export timber. Lennea does not deny this. It has also been established that Mubu Sawmilling had no valid licence to fell and export timber. Mubu Sawmilling however had a valid milling licence. The confusion apparently arose from the belief by Lennea (and I accept on the evidence before me a genuine held belief) that whilst Mubu Sawmilling had no licence to fell timber, that was going to be done by the Landowners themselves and supply them to Mubu. It was a very attractive proposition to Lennea though somewhat mistaken, because as events were to show, there were other competing landowners laying similar claims to the same land.
More or less the same arguments wereed in the case of Forestorest and Another v. Mahlon Ali and the Attorney-General CC 1/94 judgment delivered on 12 April 1994, in which it was held that Mahlon Ali trading as Hovah & Hardwood Enterprises, despite his claim being a landowner that he could fell the trees himself and extract them for milling or export through his milling licence, it was held by the court that he needed a separate licence to fell and export timber. In order to obtain a felling licence he needed a timber rights agreement from the landowners and duly approved by the Minister responsible. Mahlon Ali had no valid timber rights agreement and so the footnote attached to his milling licence was struck out by the court. That judgment set the precedent that a person wishing to fell and extract timber for milling or export, cannot do so without a valid timber rights agreement.
p class="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> Mubu Sawng fell squarely on all fours within the same category. It . It could not fell and extract timber for export or milling without a valid timber rights agreement duly approved by the Minister under section 12 of the Forest Resources and Timber Utilisation Act. The distinction however which Lennea sought to highlight in evidence before the Court was that the felling of trees was not going to be done by Mubu Sawmilling but by the landowners themselves. His argument was that Mubu Sawmilling did not require a timber rights agreement and therefore a felling licence, because the felling of the trees was going to be done by the landowners themselves. As owners of the trees they were entitled to do what they want with the trees. Unfortunately, as pointed out, this did not work out as the claim of those landowners was subsequently challenged by other landowners.
What is important to note this is that it raises doubt in my mind that Lennea knea knew that Mubu Sawmilling needed a separate licence to fell and extract timber or that he was reckless whether that fact was true or false. His belief was that it was alright, that it was not unlawful for the landowners themselves to fell their own trees and supply them to Mubu.
Further, it appears the advice or responses given out by the Office of the Commissioner of Forests was not very helpful either in terms of making clear to him what the legal position was. This is reflected in the milling licence issued to Mubu Sawmilling still containing the same footnote earlier struck out in Mahlon Ali�s Case (ibid), even when it came up for renewal some eight (8) months after the decision in Mahlon Ali�s Case had been given. It was never deleted. That can only have added confusion instead of clarity.
On the issue of the footnote permitting the export of a certacertain quota per annum in the milling licence, Lennea admits he was aware a similar footnote had been struck off by the Court in Mahlon Ali�s Case (ibid). Unfortunately, it seems (and this is drawn from his evidence) he received confused and mixed responses from the Office of the Commissioner of Forests about the effect of that decision. To some extent I do not find this surprising or unusual. One would have expected the Office of the Commissioner of Forests to have issued some sort of circular, notice or a standard letter to all current milling licence holders advising them of the effect of the decision of the Court. There was no evidence that this was ever done. (Also note as pointed out above the footnote was never deleted even when it came up for renewal).
When all these are weighed e balance I am not satisfied it had been established shed to my satisfaction on the balance of probabilities that Lennea was fraudulent in his representations about the licences needed for export being in place. He was unshaken in evidence when strenuously cross-examined by Mr. Sullivan about his knowledge, belief and understanding of the licence to export timber being in place. He firmly believed (albeit mistaken) the milling licence held by Mubu was sufficient to enable a certain quota of logs to be exported per annum, in spite of the decision in Mahlon Ali�s Case. That respectfully, is evidence that he did not know, or was reckless that Mubu Sawmilling had no valid licence to export timber under its milling licence. When his subsequent conduct is also taken into account, that only strengthens the view that his representations were not fraudulent and intended to mislead the Defendant. The defence of fraudulent misrepresentation accordingly must be dismissed.
BREACH OF THE ORIGINAL AGREE
lass="Mss="MsoNormal" style="margin-top: 1; margin-bottom: 1"> Paragraph 18(a) of the submissions of thendant: this referred to the late payment of USD37,000.00. I have already dealt with this matter in detail and do not need to repeat myself. I do not find any breach under this submission.
Paragraph 18(b)an> this raised the submission that ICM failed to have any timber lawfully ready for lifting at any time and failed to pay the guaranteed minimum monthly amount of USD200,000.00. From the undisputed evidence of Lennea there was already on the ground some 1,600 m3 of fallen logs. It should be noted too however that in his letter to the Commissioner of Forests (see File of the Commissioner of Forests identified as Exhibit �A�, folio 14, para. 2) Lennea states there were ��about 6,500m3 of Instia on the ground on Stirling and Mono��. In addition he states: �The rest of the timber on the ground is on various locations on Mono and is mix species approximately 6,000m3 in total.� It is not correct therefore that ICM failed to have any timber lawfully ready for lifting at any time. The evidence adduced does not support this submission.
On the submission that ICM failed to pay the guarantinimum monthly amountmount of USD200,000.00, the answer to this respectfully is that the Agreement was never and could not be commenced before it was terminated; the Defendant therefore was never entitled at any time to the guaranteed minimum payment. Accordingly there was no failure on the part of ICM to pay that amount.
Paragraph 18(c): this raised the submission that ICM was in breach of its obligations by requiring the helicopter for unlawful purposes at all times. The first argument raised by the Defendant was that ICM had no agreement with Mubu to extract logs for export (Ex. 18). Unfortunately this is a narrow construction of the rights of the parties to enter into contract with each other on mutual terms. There has never been any dispute between them and neither been proved, that ICM had no agreement with Mubu or any right to extract logs for export or milling. The evidence rather showed it was an accepted arrangement between them that ICM would be responsible for the extraction of logs whether for export or milling. The fact the agreement between them (Ex. 18) is silent does not affect the fact that a term can be implied, or in the alternative, that there existed a verbal agreement between them. This first argument has no basis.
class="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> The second argument raised was that neither ICM nor Mubu had a valid licence to fell and export. The fact that ICM had no valid licence to fell and export had never been denied by Lennea. Similarly it had not been denied to a certain extent by Lennea that Mubu had no valid licence to fell and export. What apparently had caused confusion among logging circles it seems was the inter-relationship between the issue of a milling licence and the rights to fell and export. Initially it was held that it was alright to have a milling licence without a separate licence to fell and export. This meant timber can be felled under a milling licence for milling as well as for export under a quota system authorised by the Commissioner of Forests. Mubu�s milling licence was obtained on 9th February 1994. Included in that licence was a foot note (para. (iii)) which permitted the export of a quota of 20,000 m3 of round logs. At the inception of the milling licence, this was perfectly valid. Further, it appears (there is little evidence to show otherwise) there was little dispute or challenge, to the persons claiming ownership rights over the customary land initially. It was only after operations had commenced that land ownership disputes arose. Also, it was only after the decision in Mahlon Ali�s Case (ibid) had come out on 12th April 1994 that the foot note was invalidated. Lennea concedes he was aware of this, but there appear to be little or no direct communication at all from the Office of Commissioner of Forests, concerning the effect of this decision on the licence held by Mubu. As pointed out, there was no evidence to show that Mubu was ever directly informed by the Commissioner of Forests, either by letter or notice, cancelling the foot note in its licence. As already noted there appear to be confusing or mixed responses to Lennea�s queries on this, which only added confusion to the issue instead of clarity as far as he was concerned.
<
Legally nevertheless, that issue han settled once and for all all in Mahlon Ali�s Case. From 14th April 1994 therefore, it was unlawful for Mubu or any other person without a valid timber rights agreement duly approved by the Minister, to fell and export timber. In that respect it would be correct to argue that Mubu had no valid licence to fell and export.
In spite of that, it is pertinent to bear in mind that the personal knowledge, belief and understanding of Lennea of the effect of this order as already pointed out was not as clear cut and simple. I have referred to the confusing responses from the Office of the Commissioner of Forests coupled with the fact that at no time was Lennea formally notified that the foot note was invalid and that it should be deleted. Further I had pointed out the discrepant act in not having the foot note deleted when the licence came for renewal on 9th February 1995. lass="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> To say therefore that the helicopter was red for unlawful purposes at s at all times is not entirely correct. It has not been proven to my satisfaction on the balance of probabilities that when the Agreement was negotiated in May 1995, Lennea took cognizance of the effect of the decision in Mahlon Ali�s Case. Also bearing in mind that Mubu had a valid milling licence, it does not necessarily follow that because there was no licence to fell and export, that the use of the helicopter for haulage of logs would be subsequently unlawful. Bearing in mind that initially it was alight to use the milling licence for purposes of felling and export, and that already trees had been felled (some 1,600 m3 or more than 6,000 m3 on Mono and Stirling Island), the helicopter would be required to haul those logs at any rate. I fail to see how that would amount to unlawful use. It is also relevant to note that even when the injunction was imposed, it was subsequently varied to enable the Plaintiff remove and export the logs already felled. That couldn't have amounted to any unlawful use of the helicopter.
p class="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> In addition, it is important to appreciaat the Defendant was requirequired only to haul logs from the stump to the dump point. There is nothing particularly unlawful about that. The Defendant was not required to fell the trees or to export them, nor be a party to any of these activities. Those were matters for the Plaintiff, Mubu Sawmilling and the landowners who claimed ownership over those trees, to worry about and address. His (that is the Defendant's) was a separate job altogether.
The third argument raised was that by 19th June 1995, Mubu�s licence had already been suspended. Unfortunately the same reasons given above also apply to this submission. Trees had already been felled by this time and hence a helicopter would be required at any rate to uplift those logs.
The fourth argument raised pertained to the purported export of kwila logs without a valid permit. This meant the Defendant submits, the Plaintiff was intending to use the helicopter for unlawful purposes. Unfortunately it is clear on evidence the Plaintiff had taken steps to have that matter sorted out. Exhibit 26 is a copy of the letter of Lennea to the Commissioner of Forests seeking permission to export those logs (bearing in mind according to his letter there was a substantial amount of kwila logs already on the ground). Further, folio 15 of Exhibit �A� for identification purposes disclosed that a recommendation had been given by the Principal Forest Officer that permission be granted for the export of the logs already felled. It was not correct therefore to assume that no permit would have been given in the event a helicopter had been made available. The matter was never pursued further because the blanket restraining order meant there was no point in bringing in a helicopter for Mono. ass="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> I do not agree therefore that the absence of a permit to fell and export kwila meant no permission would subsequently be given to have those kwila logs already felled on the ground, to be extracted and exported such that the use of the helicopter would be unlawful.
Paragraph 18(d): the submission sought to be raised under this ground was that kwila (Instia Bijuga or ironwood) is a protected species under The Forest Resources and Timber Utilisation (Protected Species) Regulations 1990 and therefore specific authority was needed for its export. Respectfully however, I have also already indirectly dealt with this matter above. Lennea appears to have been aware of this requirement and so had written under letter dated 4th January 1996 for that very purpose for permission to export kwila. I am not satisfied accordingly that this requirement would have been deliberately overlooked by the Plaintiff.
In concn, it is also pertinent to point out that it would not be be entirely correct to say that at all times the helicopter was required for unlawful purposes. When the injunction was slapped on, Lennea �agreed� that the helicopter be redeployed in PNG. He did not insist that it be brought over to be used at Mono. He conceded it would not be right to do so. Only when it was partially discharged and he was permitted to re-enter, to extract logs already felled, did he seek to have the helicopter brought into the country again. Note, Grouse did agree and sought to make attempts to bring over the helicopter, but couldn�t only because of legal obligations to third parties using the helicopter. If it was going to be used for an unlawful purpose, surely Grouse would not have consented to the arrangements for the helicopter to be brought over to the Solomons. Respectfully, I find no breach of the original agreement by the Plaintiff as submitted by the Defendant.
NOVATION OR VARIATION:>
The legal issues arising from this submission have already been dealt with and I do not need to repeat myself
p class="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> FRUSTN - THE LAW:
The doctrine of frustration arises wheis alleged that a change ofge of circumstances after the formation of the contract has rendered it physically or commercially impossible to fulfil the contract or has transformed performance into a radically different obligation from that undertaken in the contract (see Chitty on Contracts General Principles 26th Edition paragraph 1631). The learned Author in Chitty on Contracts had put forward a test for frustration formulated from Davis Contractors Ltd. v. Fareham U.D.C. [1956] UKHL 3; [1956] A.C. 696, 729, and other cases (National Carriers Ltd v. Panalpina (Northern) Ltd [1980] UKHL 8; [1981] A.C. 675, 693; Pioneer Shipping Ltd. v. B.T.P. Tioxide Ltd. (The Nema) [1982] A.C. 724, 752 ) as follows:
ass="MsoNoMsoNormal" style="margin-left: 36.0pt; margin-top: 1; margin-bottom: 1"> �If the literal words of the contractual promipromise were to he enforced in the changed circumstances, would performance involve a fundamental or radical change from the obligation originally undertaken?�
class="Mss="MsoNormal" style="margin-top: 1; margin-bottom: 1"> In that situation Lord Radcliffe in Davis Contractors Ltd (ibid) states:
��frustration occuenever the law recognises tses that without default of either party a contractual obligation has become incapable of being performed because the circumstances in which performance is called for would render it a thing radically different from that which was undertaken by the contract. Non haec in foe-dera veni. It was not this that I promised to do � There must be � such a change in the significance of the obligation that the thing undertaken would, if performed, be a different thing from that contracted for.�
class="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> Lord Reid he test for frustration in a similar way: <
�The question is whether the contract which theh they did make is, on its trite construction, wide enough to apply to the new situation: if it is not, then it is at an end.� (Page 721).
In Nationaliers Ltd. v. Panalpina (Northern) Ltd., (ibid at page age 700) Lord Simon restated the test as follows: class="MsoNoMsoNormal" style="margin-left: 36.0pt; margin-top: 1; margin-bottom: 1"> �Frustration of a contract takes place when there supervenes an event (without default of either party and for which the contract makes no sufficient provision) which so significantly changes the nature (not merely the expense or onerousness) of the outstanding contractual rights and/or obligations from what the parties could reasonably have contemplated at the time of its execution that it would be unjust to hold them to the literal sense of its stipulations in the new circumstances; in such case the law declares both parties to be discharged from further performance.�
THE FRUSTRATING EVENT:
This brings me dress one of the crucial questions in this case. What caused the contract to be frustrated? The Defendant submits it was the absence of all necessary licences and permits which was the real frustrating cause of the events (the series of injunctions) leading to impossibility of performance. Respectfully however, I do not agree. The real frustrating cause was the same old story - the dispute over land ownership by competing customary land owners. That frustrated the Agreement between the parties. That meant even if the helicopter was to be made available towards the end of January 1996, the Plaintiff would not be able to comply with his part of the bargain in view of the blanket restraining order re-imposed.
In the judgment of his Lordship, Awich J., in the casJohn Havea and Iva Ivan Maike v. Mubu Sawmilling (a firm) and Six Others, CC 178/95 judgment delivered on 12th September, 1995, his Lordship identified at page 2 the serious issue as follows:
�The serious issue is whether Lotikeni and Defendants 3, 4 and 5 own the land in question to the exclusion of Havea Maike and Miriki, the Plaintiffs. They (the Plaintiffs) have alleged ownership and the right to be consulted as the basis for their claim.�
Lotikeni and Defendants 3, 4 and 5 were the landowners who clai claimed the right of ownership over the land in which the trees were to be felled and supplied to Mubu Sawmilling. The Plaintiffs were the opposing landowners over the same land.
Even if ICM and Mubu Sawmilhad all the necessary licences and permits, there is e is no guarantee that the land would be free from dispute and litigation, hence absence of any injunction. The issue of all necessary licences and permits is no guarantee that the true customary landowners had been identified and granted rights over the timber. This perhaps is the underlying weakness of the procedure set out for acquisition of timber rights over customary land in sections 7 and 8 of the Forest Resources and Timber Utilisation Act (Cap. 40). As early as 1990, Commissioner Crome pinpointed this weakness with simplicity and clarity in the case of Fugui & Another v. Solmac Construction Company Limited and Others (1980) SILR 100 at page 106 and 107. I quote:
�All a licence amounts to, it seems, is a defence to a prosecution under s. 4(1) and the possibility that the true customary owners of timber rights and any persons by whose consent the exploitation of those rights can be sold or dealt in, have been traced as a result of the lengthy procedures under the Act. No guarantee is given that the contracting customary owners are the true owners.�
The effect of this weakness, or flaw, if one wants to call it that, has been felt over and over and over again in almost all logging operations. To hear of a logging operation involving a major logging company in the country that has commenced operations smoothly without some form of major land dispute is very rare indeed. This has been the common thread in almost all logging operations over customary land. Disputes that occur in such logging operations normally arise between landowners themselves, and not with the logging operator, and in many instances this had resulted in the Court issuing interlocutory orders restraining any logging operations until determination of the issues outstanding between the landowners. Starting at the High Court, the matter eventually usually winds its way back down to the Chief's Committees and the Local Courts for determination on matters arising in custom, quite often on questions of customary rights over the land in which the trees were situated.
Any customary landowner therefore, claiming rights of ownership over the land and trees, has the right at any time, to challenge the ownership issue in the appropriate manner, irrespective of the issue of licences and permits. If successful, this puts an end to the rights of the landowners claiming rights over the trees and the issue of licences and permits; unless the true owners themselves in turn decide to enter into a new and separate agreement with the logging company.
In this case ther even if all the necessary licences and permits may h have been issued, it would not have made much difference to the fact that the operation would have been subjected to litigation in any event, in that the dispute ran much deeper than the issue of the licences and the permits. It related to the question of ownership and rights over customary land and the trees located on that land.
This with respect dispos the submissions raised in paragraph 26 and 29 of thef the Defendant�s submissions arguing that the principles in Walton Harvey Ltd v. Walker and Homfrays Ltd [1931] 1 Ch 274 (CA) and Ockerby & Co. Ltd v. Watson (1918) 26 CLR 431 would apply so that the Plaintiff would not be able to rely on frustration.
The principle in Walton Harvey�s Case was that where one one party has special knowledge and so could have foreseen the frustrating event and conceals that knowledge from the other, the party with the special knowledge is not discharged. The argument of the Defendant in the light of this case [para. 29(2)] was that Lennea, who must be taken to have known that ICM�s legal position was in doubt, concealed the fact that ICM was relying on Mubu�s Milling Licence when he knew that the export foot note had been invalidated by the High Court.
In the evidence adduced before this Court however, I am not satisfied it had been proven on the balance of probabilities that Lennea concealed the fact that he knew that the export footnote had been invalidated by the High Court. He conceded in evidence it was common knowledge among logging circles that the footnote had been struck out in a particular case (Mahlon Ali�s Case - ibid). However, he also pointed out in evidence when the matter was expressly raised with the Office of the Commissioner of Forests, the advice given appeared to be conflicting and confusing. I had found this to be so on the evidence before me; that it caused more confusion than clarity. I had also noted this was consistent with the fact that no notice, circular, or letter, was issued to all licence holders advising them of the same. Also when the licence came up for renewal some eight months after that court decision, the footnote was not deleted. My conclusions, that Lennea did hold a genuine albeit mistaken belief regarding Mubu�s Milling Licence to export a certain quota of logs per year also apply to this submission. His subsequent actions too were consistent with this belief When these are put together, I am not satisfied the submission on concealment can be allowed to succeed.
<
The second principle relied on in
(ibid) was was that where one party warrants or represents that the contract is entered into on a particular basis, that party will not be excused by frustration but rather will be held to have assumed the risk that the contract could not be performed by reason that the presumed basis of the contract did not exist.
The argument of the Defendant (see paragraph 29(l)) was that ICM had represented that it had all the necessary licences and permits and the absence thereof was the real frustrating cause of the events (the series of injunctions) leading to impossibility of performance. I have however already dealt with this matter above when addressing the issue about what was the frustrating event in this case and do not need to repeat myself. The stated principle in Ockerby�s Case does not apply in this case.
The third argument raised [para. 29(3)] that ICM was persistently in breach b by insisting that ATL operate unlawfully, has also been dealt with.
THE LAW REFORM (FRUSTRCONTRACTS) ACT 1943 (UK):
Does this piece of Uniteddom legislation apply in Solomon Islands? In Scheduleedule 3 to the Constitution Clause 1 states:
�Subject to this Constitution and to any Act of Parliament, the Acts of the Parliament of the United Kingdom of general application and in force on 1st January 1961 shall have effect as part of the law of Solomon Islands with such changes to names, titles, offices, persons and institutions, and as to such other formal and non-substantive matters, as may be necessary to facilitate their application to the circumstances of Solomon Islands from time to time.�
I am satisfied the Law Reform (Frustrated Contracts) Act 1948 1948 is an Act of general application and in force on 1st January 1961.
SECTION 2(3):
The Defendant argues that section 2(3) submits the operation of the Act to specific contractual provisions dealing with termination in such circumstances. On this basis, it was submitted clause 20(b) of the Agreement was intended, on a proper construction, to ensure that ATL was paid its minimum guaranteed sum up to the date of discharge by the terminating event.
Doesion 2(3) apply to subordinate the Act to clause 20(b) of thof the agreement? Section 2(3) states:
�Where any contract to which this Act applies contains any provision which, upon the true construction of the contract, is intended to have effect in the event of circumstances arising which operate, or would but for the said provision operate, to frustrate the contract, or is intended to have effect the court shall give effect to whether such circumstances arise or not, the said provision and shall only give effect to the foregoing section of this Act to such extent, if any as appears to the court to be consistent with the said provision.�
Section 2(3) seeks to give recogn to any provision under anyr any contract which was intended to have effect in circumstances where for instance, there has been frustration. The question posed by learned Counsel Mr. Sullivan in relation to Clause 20(b) is whether it falls within what is stated in section 2(3) above. If so, he argues the minimum amount guaranteed should be paid.
Clause 20(b) reads:
class="MsoNoMsoNormal" style="margin-left: 36.0pt; margin-top: 1; margin-bottom: 1"> �Provided that both parties shall use their heir best endeavours to proceed with this Agreement and provided further that nothing herein shall release the Charterer from its obligations to pay the Company all sums due to the time of the condition arising.�
p class="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> The submns of the Defendant assumes that the Agreement was commencemenced on 15th July 1995. Unfortunately this Court's findings showed otherwise. First, the commencement date was delayed due to late payment of USD37,000.00; bearing in mind that it would take about 6-8 weeks for the helicopter to be positioned in Honiara from PNG. It was then deferred by consent, due to the injunction imposed on 18th July 1995. The Kamov 32 helicopter accordingly was redeployed in PNG. The legal consequence of redeployment was that it became subject to contractual obligations to third parties so that by the time the injunction was partially lifted and the helicopter required on or about 23rd November 1995, it could not be made available immediately, or within the December 1995 period and early part of January 1996. The Agreement thus simply could not be commenced within that period until the re-imposition of the blanket restraining orders signalled its demise. In other words, the Agreement ultimately was never commenced until its termination on or about 15th January 1996. The Defendant therefore cannot rely on the provisions of the Agreement for any guaranteed minimum payments.
SECTION 1(2):<
<
The appropriate section therefore which applied to this case is section 1(2) of the Law Reform (Frustrated Contracts) Act 1943. That section reads:
�All sums paid or payable to any party arty in pursuance of the contract before the time when the parties were so discharged (in this Act referred to as �the time of discharge�) shall, in the case of sums so paid, be recoverable from him as money received by him for the use of the party by whom the sums were paid, and, in the case of sums so payable, cease to be so payable:
Provided that, if the party to whom the sums were so paid or payable incurred expenses before the time of discharge in, or for the purpose of, the performance of the contract, the court may, if it considers it just to do so having regard to all the circumstances of the case, allow him to retain or, as the case may be, recover the whole or an part of the sums so paid or payable, not being an amount in excess of the expenses so incurred.�
[Emphasis added]It is not in dispute the Defendan incurred expenses. It is a is also not in dispute the Plaintiff had made substantial payments to the Defendant. The central issue in contention is whether expenses had been incurred in, or for the purpose of the performance of the contract which would entitle the Defendant to recover from the sums paid and whether the court should exercise its discretion in favour of a set off, in the interest of justice.
ere are five key elements for consideration: -
/p>p class="MsoNoMsoNormal" style="margin-left: 36.0pt; margin-top: 1; margin-bottom: 1"> 1. that the Defendant had incurred expensepenses;
2. before the discharge of the contract;
3. in performance of the cthe contract; or
4. for the purpose of the performance of the contract; and
hat it is just in all the cthe circumstances to allow the Defendant to retain the whole or any part of the sums so paid or payable.
GAMERCO S.A. -v- ICM/FAIR WARNING (AGENCD (1995) EWHC QB 1; 1995 1 WLR 1226:
The case of Gamerco S.A v. ICM/Fair Warning (Agency) Ltd (1995) EWHC QB 1; 1995 1 WLR 1226 has been referred to on this particular issue. That case involved the staging of a rock concert by one of the pop groups known as Guns N Roses on a sports stadium in Madrid. The Plaintiff were the promoters of the rock concert in Madrid and had paid upfront USD412,500.00. The concert was scheduled to be held on 4th July 1992. Relevant permits for the use of the stadium had been obtained but were later revoked when it was discovered the stadium was unsafe for use. Considerable expense had been incurred on both sides. The Defendant naturally sought a set off of all or part of such expenses it had incurred under section 1(2) of The Law Reform (Frustrated Contracts) Act 1943. In his analysis of the issue of �recovery and expense� Garland J. referred to three approaches that could be adopted by him. These were: (1) the total retention approach; (2) the equal division approach; and (3) the broad discretion approach. In his assessment of these approaches, he referred to a useful commentary of the legislation by Robert Goff J. in the case of B. P. Exploration Co. (Libya) Ltd. v. Hunt (No. 2) [1979] 1 WLR 783. I quote (pp. 799-800):
p class="MsoNoMsoNormal" style="margin-left: 36.0pt; margin-top: 1; margin-bottom: 1"> �The Act is not designed to do certain things: (i) It is not designed to apportion the loss between the parties. There is no general power under either section 1(2) or section 1(3) to make any allowance for expenses incurred by the plaintiff (except, under the proviso to section ](2), to enable him to enforce pro tanto payment of a sum payable but unpaid before frustration); and expenses incurred by the defendant are only relevant in so far as they go to reduce the net benefit obtained by him and thereby limit any award to the plaintiff. (ii) It is not concerned to put the parties in the position in which they would have been if the contract had been performed. (iii) It is not concerned to restore the parties to the position they were in before the contract was made. A remedy designed to prevent unjust enrichment may not achieve that result; for expenditure may be incurred by either party under the contract which confers no benefit on the other, and in respect of which no remedy is available under the Act.�
With specific referen section 1(2), Robert Goff J. states:
�There is no discretion in the court in respect of t of a claim under section 1(2), except in respect of the allowance for expenses; subject to such an allowance ... the plaintiff is entitled to repayment of the money he has paid. The allowance for expenses is probably best rationalised as a statutory recognition of the defence of change of position. True, the expenses need not have been incurred by reason of the plaintiff's payments; but they must have been incurred in, or for the purpose of, the performance of the contract under which the plaintiff's payment has been made, and for that reason it is just that they should be brought into account.�
class="Mss="MsoNormal" style="margin-top: 1; margin-bottom: 1"> APPLICATION TO THIS CASE:
The act was terminated on or about 15th January 1996 1996. The Defendant claims it incurred expenses before the discharge of the contract in or for the purpose of the performance of the contract and that in all the circumstances it would be just to allow the Defendant to retain the whole or part of the sums so paid.
The first crucial issue is whether the so-called expenses of thof the Defendant were incurred in or for the purpose of the performance of the contract. What is the meaning of the phrase �in or for the purpose of the performance of the contract� in the context of this case. In order to answer that question, it is relevant to have regard to the terms of the contract itself and what it entailed.
In a nutshell, the contract entailed the provision of a helicopter for ha haulage of logs at Mono Island, Solomon Islands. The contract was not for the transportation and delivery of the helicopter at Honiara, Solomon Islands. It is crucial in my respectful view to make this distinction. These are two separate matters. Anything done in or towards the haulage of logs at Mono Island would fall within the term �in or for the purpose of performance of the contract�. What this meant was that once the helicopter had been delivered to the Plaintiff on site at Honiara, anything incurred thereafter by the Defendant towards ensuring that the helicopter was operable, suitable and available, for purposes of haulage of logs, would in my respectful view qualify as something done in or for the purpose of the performance of the contract. But anything done prior to the delivery of the helicopter to Honiara could not qualify.
ass="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> It is important to appreciate the difference between costs incurred for the delivery or positioning of the helicopter in Solomon Islands, as opposed to costs incurred in or for the purpose of performance of the contract. These respectfully are not the one and same thing. Costs incurred in or for the purpose of the performance of the contract, in my respectful view do not include the costs of delivery to Honiara, Solomon Islands.
Secondly it is an express term in the Agreement the costs of delivery tery to Honiara, Solomon Islands would be borne by the Defendant. See Clause 3(a) of the Agreement which states:
lass="MsoNoMsoNormal" style="margin-left: 36.0pt; margin-top: 1; margin-bottom: 1"> �At the commencementhe agreement the Company
shall meet the costs of delivery of the Helicopter to the Charterer at Honiara, Solomon Islands, and on termination therefore by efflux of time or otherwise the Charterer shall re-deliver the Helicopter to the Company at Honiara, Solomon Islands.�
[Emphasis added]
It was common knowledge between the parties and an accefact, that the helicoelicopter to be provided was not located within the country. It had to be transported from PNG to Honiara (the agreed home positioning site of the helicopter). The Agreement as drawn up accordingly took this aspect into account. In other words, those expenses incurred in the delivery of the helicopter to Honiara are those which the Defendant had expressly agreed to bear under the agreement. It is a risk that he had expressly agreed to bear in exchange for the provision of a helicopter service in Solomon Islands. This is fortified by Clause 12(b) of the Agreement, which provided that the payment of USD37,000.00 was refundable.
�It shall be the responsibility of the Charterer to bear the costs of positioning of the helicopter from Honiara to the work site and at the termination of this Agreement, to bear the costs of redelivery of the Helicopter to Honiara.�
Clause 3(b) couldn�t be any clearer. When read with clause 3(a), it is clear where the delivery site is. This in my respectful view is a crucial term in the Agreement. It makes clear where the helicopter is to be collected or returned and also defines when responsibility arises. In other words, responsibility and therefore liability commences and ends on delivery at Honiara for each party. Anything beyond that must be borne by the parties themselves.
class="MsoNoMsoNormal" style="margin-top: 1; margin-bottom: 1"> WOULD IT BE JUST IN ALL THE CIRCUMSTANC THE CASE TO ALLOW THE DEFE DEFENDANT TO RECOVER THE WHOLE OR PART:
The second and final crucial issue to consider under the proviso is whether er it would be just in all the circumstances of this case that the Defendant be allowed to recover the whole or part of the sums paid. Taking everything into account, I am also not satisfied that any recovery should be allowed save for the costs of fuel and transportation which the Plaintiff had received benefit of. OROF THE COURT:
/p>
SMISS COUNTER-CLAIM OF THE THE DEFENDANT.
2. AWARD JUDGMENT MENT IN FAVOUR OF THE PLAINTIFF FOR THE SUM OF USD37,000.00, PLUS SBD211,520.00 (SEE EXHIBIT 12) TOGETHER WITH INTEREST FROM 22ND MAY 1996 (DATE ACTION COMMENCED IN THE HIGH COURT) AT 5%.
3. COSTS OF THE PLAINTIFF IN F IN THIS ACTION ALSO TO BE BORNE BY THE DEFENDANT.
THE COURT
PacLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback
URL: http://www.paclii.org/sb/cases/SBHC/1999/4.html