KD Enterprise Ltd v Vanuatu Waikee Group International Industrial Co Ltd [2020] VUSC 225; Civil Case 108 of 2020 (17 September 2020)
IN THE SUPREME COURT OF Civil
THE REPUBLIC OF VANUATU Case No. 20/108 SC/CIVL
(Civil Jurisdiction)
BETWEEN: KD Enterprise Limited
Claimant
AND: Vanuatu Waikee Group International Industrial Company Limited
Defendant
Date of Trial: 3 September 2020
Before: Justice V.M. Trief
In Attendance: Claimant – Mrs M.G. Nari
Defendant – Mr D. Yawha
Date of Decision: 17 September 2020
JUDGMENT
- Introduction
- The Claimant KD Enterprise Ltd (‘KD Enterprise’) supplied sand and coral aggregate to the Defendant Vanuatu Waikee Group
International Industrial Company Limited (‘Waikee Group’). It is seeking payment of an unpaid invoice. KD Enterprise
is also seeking damages in relation to its purchase of spare parts for a Hitachi excavator owned by the Waikee Group. The parties
had entered into a sale and purchase agreement for KD Enterprise to buy the excavator. That agreement was cancelled but after KD
Enterprise had already purchased spare parts to repair the excavator. Waikee Group agreed to buy those spare parts and then later
refused to. KD Enterprise is seeking damages for the monies it spent on the spare parts.
- Background
- It is undisputed that:
- KD Enterprise supplied sand and coral aggregate to Waikee Group for construction purposes for its project at Velit Bay, Santo at the
agreed price of VT3,600 per cubic metre (‘m3’) inclusive of VAT.
- Waikee Group has not paid KD Enterprise’s invoice dated 18 June 2019 for the supply of sand and coral aggregate.
- On 9 September 2018, the parties entered into a Sale and Purchase Agreement for the sale of Waikee Group’s Hitachi excavator
to KD Enterprise for VT4,000,000 (‘S & P Agreement’).
- KD Enterprise then purchased spare parts to repair the excavator.
- By email on 14 November 2018, Waikee Group cancelled the S & P Agreement and said that it would purchase the spare parts from
KD Enterprise.
- On 14 December 2018, Waikee Group requested a review of the price of the spare parts.
- On or about 10 May 2019, Waikee Group refused to buy the spare parts.
- In July 2019, the parties discussed buying the excavator at a lower price if KD Enterprise would pay tax on the machine. Ultimately
they abandoned that course as no import duty was ever paid by Waikee Group as it had a duty exemption.
- On 2 August 2019, KD Enterprise advised that they had bought their own excavator and no longer needed to buy the Waikee Group’s
machine.
- Discussion
Supply of sand and coral aggregate
- The Waikee Group does not dispute that the agreed price for KD Enterprise’s supply to them was VT3,600/m3 inclusive of VAT.
However, the invoice for which payment is sought sets out unit prices for white and black sand of VT4,200 and VT5,500 per m3, and
a unit price of VT4,800/m3 for coral aggregate. These unit prices exceed the agreed price.
- According to the invoice dated 18 June 2019, KD Enterprise supplied 924 m3 of coral aggregate, 50 m3 of white sand (screened) and
28 m3 of black sand, totalling 1,002 m3 of sand and coral aggregate. Waikee Group did not dispute that this quantity of materials
had been signed for when the materials were collected.
- I am satisfied that KD Enterprise has proved on the balance of probabilities or that it is more likely than not that it supplied Waikee
Group 1,002 m3 of sand and coral aggregate materials for which it has not been paid. At the agreed price of VT3,600/m3 inclusive
of VAT, the amount that Waikee Group must pay KD Enterprise is VT3,607,200. I will enter judgment accordingly.
Purchase of spare parts for the Defendant’s excavator
- On 9 September 2018, the parties entered into the S & P Agreement for KD Enterprise to buy Waikee Group’s excavator. KD
Enterprise then bought spare parts to repair the excavator. Before it could repair the machine however, the Waikee Group by email
on 14 November 2018, cancelled the S & P Agreement and said that it would purchase the spare parts from KD Enterprise. It expressly
stated that it was aware that KD Enterprise had already bought spare parts to fix the excavator, requested an ‘actual value
calculation of those parts’ and that it would buy the parts.
- On 14 December 2018, Waikee Group requested a review of the price of the spare parts. On or about 10 May 2019, Waikee Group refused
to buy the spare parts.
- The parties did not ever agree the price at which Waikee Group would buy the spare parts from KD Enterprise. Accordingly, I am not
satisfied that there was an agreement between the parties as to the purchase of spare parts from KD Enterprise.
- However, I am satisfied on the facts that there was a negligent misrepresentation by the Waikee Group to KD Enterprise that it would
sell it the excavator. This led to the parties entering into the S & P Agreement and then KD Enterprise purchasing spare parts
to repair the excavator. Subsequently Waikee Group cancelled the S & P Agreement when it formed the view it could not sell a
machine that it had imported duty-free. This resulted in KD Enterprise suffering loss as it had already expended monies on the spare
parts.
- Nowhere in the evidence before me are there any actual receipts for the purchase or shipping of the spare parts to Vanuatu. I am therefore
not in a position to determine the amount of damages that the Waikee Group should pay to KD Enterprise in relation to its purchase
of the spare parts. In the circumstances, I will enter judgment for KD Enterprises for damages in an amount to be determined in relation
to its purchase of spare parts for the excavator.
- Result and Decision
- Judgment is entered for the Claimant as follows:
- The Defendant is to pay the Claimant VT3,607,200 for the supply of sand and coral aggregate.
- The Defendant is to pay the Claimant damages in an amount to be determined in relation to the Claimant’s purchase of spare parts
for the excavator.
- The Defendant is to pay the Claimant interest on the judgment sums at 5% p.a. from the df judgment uent until completion of payment
of those sums.
- Costs should follow the event. The Defendant is to pay the Claimanaimant’s costs as agreed, or taxed by the Master. Once settled,
the costs are to be paid within 21 days.
DATED at Port Vila this 17th day of September 2020
BY THE COURT
.................................................
Viran Molisa Trief
Judge