Home
| Databases
| WorldLII
| Search
| Feedback
National Court of Papua New Guinea |
PAPUA NEW GUINEA
[IN THE NATIONAL COURT OF JUSTICE]
OS NO.126 OF 2013
BETWEEN
BIOMA EKAMO HOLDINGS LIMITED
Plaintiff
AND
MARC ORISURU AVAI – ADMINISTRATOR, GULF PROVINCIAL ADMINISTRATION
First Defendant
AND
GULF PROVINCIAL GOVERNMENT
Second Defendant
AND
DR. PETER GA’ALLAH KORA (PhD) – SECRETARY, DEPARTMENT OF NATIONAL PLANNING & MONITORING AND CHAIRMAN OF THE ECONOMIC
IMPLEMENTATION COMMITTEE
Third Defendant
AND
DEPARTMENT OF NATIONAL PLANNING & MONITORING
Fourth Defendant
AND
STEVEN GIBSON, DEPARTMENT OF FINANCE
Fifth Defendant
AND
DEPARTMENT OF FINANCE
Sixth Defendant
AND
RENDEL RIMUA – SECRETARY, DEPARTMENT OF PETROLUEM & ENERGY
Seventh Defendant
AND
DEPARTMENT OF PETROLUEM & ENERGY
Eighth Defendant
AND
THE INDEPENDENT STATE OF PAPUA NEW GUINEA
Ninth Defendant
Waigani: Makail J
2014: 3rd, 12th December
2016: 23rd May
CIVIL – Money claim – Withholding of funds – Infrastructure Development Grants – Funds for projects within
Petroleum Pipeline areas – Oil & Gas Act, 1998 – Section 173
CIVIL – Infrastructure Development Grants – Approval of – Authority to approve projects and funds – Funds
for projects within Petroleum Pipeline areas – Expenditure Implementation Committee – Procurement procedure for tender
and award of contracts – Oil & Gas Act, 1998 – Sections 173 & 178 – Public Finance (Management) Act, 1995
– Part VII
No cases cited:
Counsel:
Mr. M. Kombri, for Plaintiff
Mr. S. Ketan with Ms. M. Peipul, for First and Second Defendants
Mr. C. Mende, for Third and Fourth Defendants
No appearance, for Fifth to Ninth Defendants
JUDGMENT
23rd May, 2016
1. MAKAIL J: This is a money claim. The plaintiff is a company incorporated under the provisions of the Companies Act, 1997. It claims to be a landowner company and commenced these proceedings by originating summons to seek, amongst other things, declaratory
relief, that a committee called the Expenditure Implementation Committee (“EIC”) is the only authorised body to approve funds for infrastructure projects under clause 13.1 (e) of the PNG LNG Pipeline Licence Benefit Sharing Agreement dated 26th November 2009 (“LBSA”), that the first and second defendants had no authority to approve or withhold funds, and an order for payment of a sum of K9,500,000.00.
2. This sum, it alleged, was part of K50,000,000.00 approved in 2011 by the EIC chaired by the third defendant, to fund the construction
of an office complex for the Gulf Provincial Administration and Apeawa Water Supply in Kikori under the infrastructure projects programme
within the pipeline areas where pipes for the Liquefied Natural Gas (“LNG”) project run. These funds are referred to as or called “Infrastructure Development Grants” (“IDG”) and are catered for by the State under LBSA.
3. The State is obliged by Statute to pay these funds to affected Local-level Governments and affected Provincial Governments where
the resource projects are located. Section 173 of the Oil & Gas Act, 1998 provides for these funds in these terms:
“173. Project grants.
(1) In addition to the other benefits granted to affected Local-level Governments and affected Provincial Governments under this Part, the State shall make grants to affected Local-level Governments and affected Provincial Governments of a petroleum project in accordance with this section.
(2) The State shall in a development agreement and may in any other agreement agree with the affected Local-level Governments and affected Provincial Governments of a petroleum project upon the amount and nature and timing of grants to be made by the State to those affected Local-level Governments and affected Provincial Governments in relation to the petroleum project.
(3) Grants made in accordance with this section may be in the form of monetary payments or in the form of provision of infrastructure or services or other benefits.
(4) The provision to an affected Local-level Government or an affected Provincial Government of a benefit in the form of infrastructure (or any other benefit) which is funded by the licensee in respect of the petroleum project pursuant to Section 219C of the Income Tax Act 1959 shall be taken to be a grant made in accordance with this section.
(5) The State may, in addition to grants made to affected Local-level Governments or affected Provincial Governments under this section, make grants to project area landowners or customary owners of land in a petroleum project area.”
4. The expenditure of the funds, establishment, composition and functions of the EIC are set out in section 178 of the Act. Section 178 states:
“78. Expenditure on behalf of affected Local-level Governments and affected Provincial Governments.
(1) All grants made in accordance with Section 173, and all monies held on behalf of an affected Local-level Government or affected Provincial Government in accordance with Section 176 and available to be spent by the affected Local-level Government or affected Provincial Government, shall be administered in accordance with this section.
(2) The Minister shall establish, in respect of each petroleum project, an Expenditure Implementation Committee comprising-
- (a) the Secretary of the Department of National Planning or the department responsible for national planning matters, who shall be the Chairman; and
(b) the Director; and
(c) the Secretary of the Department of Treasury or the department responsible for national government finances; and
(d) the Secretary of the Department of Works and Transport; and
(e) the Secretary of the Department of Provincial and Local-level Government Affairs; and
(f) the Administrator of each affected Provincial Government or District Administrator responsible for an affected Local-level Government; and
(g) the chief executive of the Operator who shall represent the licensees of the petroleum project,
ټ#160;< < ټ &<;< or their heir representat
(3) Expenditure of monies referred to in Subsection (1) by or on behalf of an affected Local-level Government or affected Provincial Government and the implementation of grants referred to in that subsection shall be made only-
- (a) in accordance with development plans submitted by the relevant Local-level Government or Provincial Government; and
- (b) in accordance with the approval of the Expenditure Implementation Committee for the petroleum project in question.
(4) The Expenditure Implementation Committee shall be responsible for-
- (a) monitoring budgets and timetables for construction and implementation of grant and benefit expenditure on behalf of affected Local-level Governments and affected Provincial Governments, and approving such expenditure; and
(b) monitoring expenditure made pursuant to Section 219C of the Income Tax Act 1959 to ensure that project funded pursuant to that section comply with the development plans submitted by the relevant Local-level Government or Provincial Government; and
(c) monitoring the program of ongoing projects for expenditure of monies in accordance with this section.
(5) Notwithstanding the provisions of Section 219C of the Income Tax Act 1959, no expenditure by a licensee in respect of a petroleum project shall fulfil the requirements of that section unless approved by the Expenditure Implementation Committee of the petroleum project in question.” (Underlining is mine).
5. The plaintiff alleged that it submitted proposals to the EIC for the subject projects and the EIC approved them. In 2011, a sum of K9, 000,000.00 was transferred to the first and second defendants to disperse to it and they paid K5, 500,000.00 and withheld K3, 500,000.00 which is outstanding. It alleged that the first and second defendants wrongfully withheld this sum.
6. In 2012 a further K6, 000,000.00 was released by the fifth and sixth defendants to be paid to it, however, the first and second defendants withheld it. It alleged that the total withheld and owing is K9, 500,000.00.
7. The first and second defendants denied liability and argued that they have the requisite authority to withhold the funds and reasons to justify it. The reasons are:
8. Evidence was led at trial from the Provincial Administrator Mr. Marc Orisuru Avai and Deputy Provincial Administrator Mr. Christopher Uari Haro to establish these matters. But no witnesses were called by the third to the ninth defendants to give evidence in relation to the functions of the EIC and the procedure for obtaining approval of funds for projects in the affected area.
9. The plaintiff relied on section 178 (supra) and submitted that the EIC is the sole authority to screen project proposals and approve funding for projects in the affected area. This approval is not subject to further approvals by any person or authority, eg, approval under the Public Finance (Management) Act, 1995 for awarding of contracts.
10. As it was pointed out, the first and second defendants denied liability on the grounds set out at [7] above. However, they did not specifically address the application of section 178 in their submissions.
11. In my view the application of section 178 is pivotal to the entire dispute. From my reading of this provision, the key words in
this provision are “development plans”. Section 178 (3) (a).
12. This means that the “expenditure of monies” and “implementation of grants” (IDGs) are made based on development
plans. The development plans are submitted by or must come from the relevant Local-level Governments or Provincial Governments.
For instance, in this case the Local-level Government or Provincial Government must have a plan to build a road, or water supply,
or school, or health centre or all of them in the pipeline project area.
13. Where it plans to engage in such a project, it must prepare a development plan and submit to the EIC. I should add that the development plan should not be confused with a project proposal. They are two different documents. One is a plan and the other is a proposal.
14. Secondly, in section 178 (3) (b) the key word is “approval”. In my view this means that the expenditure of funds or grants will be considered and approved by the EIC based on the development plan submitted by the Local-level Government or Provincial Government.
15. Finally, in section 178 (4) (a) the EIC is responsible for monitoring budgets and timetable for construction and implementation of grant and benefit expenditure on behalf of the affected Local-level Governments or affected Provincial Governments and approving such expenditure.
16. There is no mention of approval of awarding of contract to an applicant for project and funding by the EIC. Neither is there any reference to a “project proposal” in this provision. So where is the authority of the EIC to consider and approve “project proposal”? I am unable to find any in this provision.
17. I come to the conclusion that contrary to the plaintiff’s strong argument that the EIC has the requisite authority to screen project proposals and approve funding for projects in the affected pipeline area, I find none.
18. The term “project proposal” appears in Clause 13.1 (d) of the LBSA and appears to be the basis for the plaintiff’s argument that the EIC is the authorised body to consider project proposals and approve funding. Clause 13.1 states:
“13. IMPLEMENTATION MECHANISM
The parties acknowledge the following understandings reached by their representatives to the UBSA with regard to the Expenditure Implementation Committee (‘EIC’).
(a) That EIC plays an important role in implementing socio-economic and infrastructure projects in compliance with the requirements of the Public Finance (Management) Act 1995 and the Act.
(b) The parties agree that the EIC Guidelines are important in the implementation of the infrastructure projects either agreed under the Licence Based Benefits Sharing Agreements or any other infrastructure projects.
(c) The EIC will process and oversee the implementation of BSA infrastructure projects approved under each Licence Based Benefits Sharing Agreement.
(d) The project proposal submitted for funding under EIC Budget will only be approved by the EIC for expenditure when they are compatible with the EIC Guidelines and the Medium Term Development Strategy that is administered by the Department of National Planning and District Development and DPE.
(e) The Parties hereto agree that the EIC will be the authority responsible for the implementation of BSA infrastructure projects and that all projects to be undertaken are subject to the availability of funds.
(f) Where there is a change in law in relation to the EIC or as a result of a review under Clause 9, the Parties agree to work with and support any alternative implementing agency appointed by the State to succeed EIC. The State will ensure that this alternative implementing agency complies with the requirements of this Clause.”
19. Clause 13.1 (a) is quite clear. Where the EIC implements socio-economic and infrastructure projects, it must comply with the Public Finance (Management) Act, 1995 and the Oil & Gas Act, 1998.
20. Clause 13.1 (c) clarifies the role of the EIC with regard to the Benefit Sharing Agreement (“BSA”) infrastructure projects. It is responsible for processing and overseeing the implementation of projects approved under each LBSA.
21. Under clause 13.1 (d) the proposals for the projects are submitted for funding under the EIC Budget and will be approved when they are compatible with the EIC Guidelines and Medium Term Development Strategy administered by the fourth and eighth defendants.
22. In my view clause 13.1 (d) does not state that the EIC is the sole authorised body to consider project proposals and approve funding for projects. On the other hand, the EIC only approves the project proposals that are within the EIC Budget and in line with the guidelines and strategy of the National Government. In practical terms for instance, there would be no point in the EIC approving funding for projects that are beyond its budget or not in line with the guidelines and strategy of the National Government.
23. Again, there is no mention of awarding of contracts to successful applicants for projects. But to my mind, the intention of the LBSA in clause 13.1 (a) is very clear. It is intended to capture this requirement by making reference to the compliance requirements under the Public Finance (Management) Act, 1995. This means that the tender and awarding of contracts to successful applicants must go through the procurement procedure under Part VII of the Public Finance (Management) Act, 1995.
24. In its Decision No. 96/2010 the National Executive Council (“NEC”) saw the need when it was considering options available to control and manage the use of these funds back in 2010, especially where it had just approved payment of K1.2 billion as IDG funds to the beneficiaries within and along the LNG project area.
25. This is plain from Attachment “A” of the Decision where it stated:
“SCREENING AND PAYMENT OF IDG FUNDS
It is important to note that, although the State committed to provide K1.2 billion in IDG for the LNG project areas, no mechanism has been established to manage and monitor application of this fund.”
26. This is further clarified and put to rest two years later by its subsequent Decision No. 49/2012 where it:
“6. approved that the screening and prioritisation of project proposals must be done at the Provincial and District levels in consultation with the “affected Local Level Governments”
27. In this case the first problem with the plaintiff’s claim is that there is no evidence of a development plan submitted by the
Gulf Provincial Government for a plan to build a Provincial Administration Office Complex in compliance with section 178 (3) (a)
of the Oil & Gas Act, 1998. Similarly, there is no evidence of a development plan for the Water Supply project. So there is no evidence to support the
plaintiff’s assertion that the EIC unlawfully approved the subject projects.
28. The second problem is that the EIC does not have the sole authority to approve projects and funding for projects. The third problem is that there is no evidence that the plaintiff complied with the procurement procedure under Part VII of Public Finance (Management) Act, 1995.
29. The final problem is that there is no evidence of acquittals and progressive reports in relation to the status of these projects simply because the procurement procedure for tender and awarding of contracts under the Public Finance (Management) Act, 1995 have not been complied with.
30. I conclude that the awarding of the purported contracts for these two projects to the plaintiff by the EIC was done in breach of the section 178 of the Oil & Gas Act, 1998 and the Public Finance (Management) Act, 1995. They are null and void and of no legal effect.
31. It follows the plaintiff is not entitled to the relief sought. The proceeding is dismissed with costs to the first, second, third and fourth defendants.
Judgment and Orders accordingly,
_________________________________________________________
Kombri & Associates: Lawyers for the Plaintiff
Ketan Lawyers: Lawyers for the First & Second Defendants
Wantok Legal Group: Lawyers for the Third & Fourth Defendants
Solicitor-General: Lawyers for the Fifth to Ninth Defendants
PacLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.paclii.org/pg/cases/PGNC/2016/119.html