You are here:
PacLII >>
Databases >>
National Court of Papua New Guinea >>
2018 >>
[2018] PGNC 557
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Sedema Technology Ltd v Paul [2018] PGNC 557; N7720 (10 July 2018)
N7720
PAPUA NEW GUINEA
[IN THE NATIONAL COURT OF JUSTICE]
OS NO. 259 OF 2018(CC1)
BETWEEN
SEDEMA TECHNOLOGY LIMITED
Plaintiff
AND
RAY PAUL as Commissioner of Customs, Papua New Guinea Customs Services
First Defendant
AND
PAPUA NEW GUINEA CUSTOMS SERVICES
Second Defendant
AND
PHILIP ELUDEME as Chairman, Central Supply & Tenders Board
Third Defendant
AND
CENTRAL SUPPLY & TENDERS BOARD
Fourth Defendant
AND
THE INDEPENDENT STATE OF PAPUA NEW GUINEA
Fifth Defendant
Waigani: Dingake J
2018: 17th May, 21st June, & 10th July
PRACTICE AND PROCEDURE – Leave to give Notice in terms of Section 5 of the Claims By and Against the State Act – Requirements
not met – Application refused.
Cases Cited
The State v Downer Construction (PNG) Limited (2009) SC 979
Counsel
Mr. Livingstone Baida, for the Plaintiff
Mr. William Maino, for the First & Second Defendants
Ms. Tiangin, for the Third & Fourth Defendants
10th July, 2018
- DINGAKE J: This is an application made pursuant to Order 4 Rule 32 of the National Court Rules and Section 155(4) of the Constitution for leave to be granted to give a Section 5 Notice to the State in accordance with Section 5(2) (c) of the Claims By and Against the State Act.
- The applicant relies for the relief sought on the affidavit of Mr. John Pung filed of record.
- I must mention, before dealing with the merits of the application that, on the day the matter was scheduled to be heard, Mr. William
Maino counsel for the first and second respondents came more than thirty (30) minutes late. He apologised and informed the Court
that he was late on account of traffic. He did not elaborate. The Court found the explanation insufficient and barred him from appearing.
Lawyers are obliged to attend Court punctually, as scheduled, unless there are compelling reasons for coming late. Failure to attend
Court on time as scheduled amounts to contempt in the face of the Court. It assails the dignity and authority of the Court and may
be summarily punishable.
Background
- The background to this matter is that on the 30th of October, 2014, the plaintiff (applicant) filed a writ of summons against the defendants, in WS No. 1369 of 2014, for alleged breach
of contract
- In the said proceedings the applicant seeks, inter alia, damages for breach and payment, being a balance pursuant to the Contract Agreement made on the 26th of March, 2012.
- On the 15th of May, 2015, the proceedings were dismissed for want of Section 5 Notice.
- On the 24th June, 2015, the applicant being unhappy with the decision of the National Court dismissing the proceedings for want of Section 5
Notice appealed to the Supreme Court. The said appeal was subsequently withdrawn with leave of the Court, on the 14th of December, 2017.
- On the 7th of February, 2018, the applicant wrote to the Attorney General seeking an extension of time to give a Section 5 Notice to the State
as required by the Claims By and Against the State Act.
- On the 19th of February, 2018, the Office of the Department of Justice and Attorney General wrote to the plaintiff refusing the request to grant
an extension of time to give the required notice.
- On the 26th of April, 2018, the applicant filed this Motion seeking leave to be granted extension of time to give the required notice.
The Evidence
- In its supporting affidavit, the applicant avers that the delay in issuing the Section 5 Notice is attributable to negotiations between
the parties as indicated in the supporting affidavit of Mr. John Pung.
- The applicant avers that between 29th January, 2013 and 29th August, 2013, it inadvertently failed to serve a Section 5 Notice on the State.
- The applicant also avers that the delay was occassioned by the first defendant’s failure to respond to the plaintiff’s
letter of the 17th August, 2013 and the non-provision of the remaining retention funds by the second defendant to complete 30% of the project.
- In order to succeed to obtain the extension of time sought, the applicant is required to:
- (a) Give a reasonable explanation for not coming within the six (6) months period and any delays thereafter in making an application
for extension of time;
- (b) Disclose a reasonable cause of action to pursue against the State; and
- (c) Demonstrate no prejudice likely to occur to the State by any late notice (see The State v Downer Construction (PNG) Limited (2009) SC 979).
- The affidavit evidence of the applicant must be subjected to the above test.
- It is common cause that the applicant failed to give notice within six (6) months as required by the Claims By and Against State Act.
- I am aware that the parties do not agree as to when the cause of action accrued, but nothing much turns on that, having regard to
the common cause fact that the applicant concedes it is late in giving the Section 5 Notice. I am prepared to assume, as I hereby
do, in favour of the applicant, without deciding, that the cause of action accrued on the 29th of August, 2013.
- Assuming in the applicant’s favour as I hereby do, that the cause of action accrued on the 29th of August, 2013, there is no reasonable explanation given for failing to give the Section 5 Notice within the time required.
- The affidavit of Mr. Pung, at paragraph 23, simply says:
- 23. As per the contents of the correspondences from the period between 29 January, 2013 and 29 August 2013, the plaintiff concurs to have had inadertedly failed to serve a section five(5) notice on the State based on the following
grounds:
- i) Negotiations were still ongoing and there was no formal response from the First Defendant when after being served the letter dated
17 August 2013, b the Plaintiff;
- ii) Due to the non-provision of the remaining retention funds by the Second Defendant to complete thirty (30%) of the project, the
Plaintiff was unable to complete thirty (30) percent of the construction phase within thirty (30) days as per the letter specified
in Annexure “JP3” contained herein.
- It is clear from the above that the affidavit explains what happened between 29th January, 2013 and 29th August, 2013, and not the period thereafter.
- The above explanation is not a reasonable explanation for not coming within the six (6) months period required by the Claims By and Against the State Act.
- The applicant in its supporting affidavit does not give a reasonable explanation for the delays after the expiry of six (6) months.
For instance, while the Supreme Court in SCA No. 79 of 2015, granted leave on the 14th of December, 2017, to withdraw the appeal, the applicant doesn’t account for the delay of more than six (6) weeks to seek an
extension of time reckoned from the 14th of December, 2017. Such request for an extension was only sought on the 7th of February, 2018.
- Furthermore, after the Attorney General refused to grant the extension sought on the 19th of February, 2018, the applicant delayed for a period of more than two (2) months to file the current application with this Court.
There is no explanation on record for the delay between the 19th of February, 2018, when the Attorney General refused the extension, and the 26th of April, 2018, when this application was filed.
- The applicant does not demonstrate that no prejudice is likely to occur to the State by late notice.
- In the result, the application is without merit, and it is refused with costs to the defendants, (save that the first and second
defendants shall not be entitled to recover the costs for the hearing of the 10th of July, 2018).
___________________________________________________________
Nelson Lawyers: Lawyers for the Plaintiff
PNG Customs Legal Services: Lawyers for the First & Second Defendants
Office of the Solicitor General: Lawyers for the Third & Fourth Defendants
PacLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.paclii.org/pg/cases/PGNC/2018/557.html