Home
| Databases
| WorldLII
| Search
| Feedback
National Court of Papua New Guinea |
PAPUA NEW GUINEA
[IN THE NATIONAL COURT OF JUSTICE]
WS No. 645 OF 2019
DALAS PROPERTY MANAGEMENT LIMITED
Plaintiff
AND
AMRAK CONSTRUCTION & CONSULTING (PNG) LIMITED
Defendant
Waigani: Linge A J
2022: 16th & 29th August
CONTRACT – plaintiff claims for reimbursement of advance payments made to defendant – plaintiff and defendant contracted for defendant to build a swimming pool for the plaintiff – defendant failed to complete project as stated under the contract – defendant says delay in materials arriving in PNG from Australia has caused delay in completing project on time as agreed – plaintiff also claims damages for breach of contract by defendant and costs– common law doctrine of frustration of contract where an intervening act causes delay or non- performance of a contractual obligation - whether the delay in the arrival of materials from Australia to complete the swimming pool is an intervening event – delay of materials from Australia is not an intervening act – defendant has breached the agreement – liability in breach of contract by defendant established
Cases Cited:
Papua New Guinean Cases
Mand v. Lypita [2021] PGNC 106; N8857
Lyn v. Yaku [2017] PGSC 6, SC1574
PK Investment Ltd v Mobil Oil New Guinea Ltd [2015] PGSC 50; SC1456
Pacross Limited v Rouna Development Limited (2009) N3648
Suan v. Dumba [2013] PGNC 211; N5428
Overseas Cases
Hirji Mulji v Cheong S.S Co Ltd [1926] AC 497
Counsel:
Mr. Joe Sunungu, for the Plaintiff
Mr. Andrew Kuria, for the Defendant
DECISION
29th August, 2022
Facts
Submissions
For the plaintiff
For the defendant
Consideration
23. The evidence is clear, and it is not in dispute that the pool was not completed in accordance with the terms of the contract. Also, it is not disputed by the defendant that there was clear delay.
24. The defendant justifies the delay in the completion of the swimming pool as being due to the delay in the arrival of specific materials which were ordered from Australia. It maintained that it cannot undertake any work until these materials arrive.
25. On the 14 March 2019 the plaintiff exercised its right under the contract and gave notice of termination to the defendant pursuant to Article 10.2 of the Contract. The Contract was terminated after seven (7) days on the 25 March 2019.
Frustration
26. The defendant claims that the contract was frustrated by the delay in arrival of materials sourced from Australia. Defendant claims that the delay is beyond its control. He relies on PK Investment Ltd v Mobil Oil New Guinea Ltd [2015] PGSC50; SC 1456 and Pacross Limited v Rouna Development Limited (2009) N3648.
27. The common law doctrine of frustration of contract which is adopted as part of the Underlying Law under Schedule 2.3 of the Constitution, stipulates that an event that renders performance of contract impossible or radically different from originally contemplated by the parties is deemed to frustrate the contract. That is, the frustrating event or intervening event discharges the contract or makes the contract impossible to perform (see Hirji Mulji v Cheong S.S Co Ltd [1926] AC 497 at.p.505).
28. The defendant would have been aware of requirement of plaintiff for the type of pool. He wanted it to be of an Australian standard. The contract specification and drawings include all materials needed to complete the pool are the responsibility of the defendant. Specifically, Item1 under Supply & Construction, it sates “the contractor shall provide all materials and consumables to construct and install 100% completion and to client’s satisfaction.”
29. The delay of the materials from Australia as claimed by defendant is not an intervening event. This is a normal risk involved in a building contract. In my view a reliable contractor would have factored this into his contract especially in a short completion timeline of three (3) months.
30. The defendant has not adduced evidence of any natural disaster, act of God or pandemic that had caused the delay in shipping or airlifting of materials from Australia.
31. The defendant claims that payment was made to Niugini Link Pty Ltd for the specialized items from Australia but were not delivered by the time of filing this cause of action. The Customer Copy of what appears to be a quotation dated 30 August 2018 is unreliable as it shows no value of the items.
32. I distinguish both cases cited by the defendant. The delay was in the control of the defendant. In PK Investment Ltd v Mobil Oil New Guinea Ltd (Supra) the frustrating event was the landowners dispute, protests and demands for the defendants not to operate the fuel station. The plaintiff in that case was not able to even commence and perform the contract.
33. In Pacross Limited v Rouna Development Limited (Supra) the frustrating event was the injunction granted to the defendant upon application by the plaintiff to cease operation. The Court held that the operation of defendant company was frustrated upon the granting of the injunction that discharged the contract.
34. In this case the delay of specialized materials from Australia is not an event of frustration. The defendant cannot rely on it. The defendant failure to complete the construction of the swimming pool as aforesaid is a breach of Article 2 of the Contract.
35. In my view, the contract was properly terminated on the 25 March 2019 14 March 2019. The plaintiff exercised its right under the contract upon giving notice pursuant to Article 10.2 of the Contract14 March 2019.
36. The next issue to consider is the claim for reimbursement by the plaintiff for K120,000.00 from the advance/progress payment of K178,600.00 out of the total contract value of K220,000.00 plus damages and costs.
37. I will not deliberate on this at this juncture but will give liberty to parties to appear before me for an assessment of damages.
Order
Ordered Accordingly
_______________________________________________________________
Eagle Lawyers: Lawyers for the Plaintiff
Kuria Lawyers: Lawyers for the Defendant
PacLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.paclii.org/pg/cases/PGNC/2022/327.html