PacLII Home | Databases | WorldLII | Search | Feedback

Supreme Court of Papua New Guinea

You are here:  PacLII >> Databases >> Supreme Court of Papua New Guinea >> 2023 >> [2023] PGSC 7

Database Search | Name Search | Recent Decisions | Noteup | LawCite | Download | Help

Redcoco Properties Ltd v Gimiseve [2023] PGSC 7; SC2358 (23 February 2023)


SC2358


PAPUA NEW GUINEA
[IN THE SUPREME COURT OF JUSTICE]


SCA 41 & 42 OF 2021


BETWEEN:
REDCOCO PROPERTIES LIMITED
Appellant


AND:
JOHN GIMISEVE IN HIS CAPACITY AS THE CHAIRMAN OF THE EHP
SUPPLIES AND TENDERS BOARD
First Respondent


AND:
BENSON IMARA IN HIS CAPACITY AS THE DISTRICT ADMINISTRATOR OF THE GOROKA DISTRICT AND CHIEF EXECUTIVE OFFICER OF THE GOROKA DISTRICT DEVELOPMENT AUTHORITY
Second Respondent


AND:
ENOCH MIEH IN HIS CAPACITY AS THE CHAIRMAN OF THE BOARD OF GOVERNORS OF THE GOROKA SECONDARY SCHOOL
Third Respondent


AND:
LESTER MITIGEI IN HIS CAPACITY AS THE DEPUTY PRINCIPAL OF
GOROKA SECONDARY SCHOOL
Fourth Respondent


AND:
GOROKA SECONDARY SCHOOL
Fifth Respondent


Waigani: Kassman, Logan, Polume-Kiele
2022: 22nd August
2023: 23rd February


CONTRACTS – construction contracts – meaning of “lump sum” contract – where parties stipulate that contract to be a lump sum contract – where parties also stipulate process for making progress claims and progress payments – held: where parties include contractual stipulations for progress claims and payments, the parties will be taken to have intended that the contract price will be fixed, albeit paid by instalments


EQUITY – restitution – recovery of funds paid pursuant to illegal or unenforceable contracts – where building contract entered into with public body subject to Public Finance (Management) Act 1995 – where contract did not comply with requirements for public tender or approval by Minister – where public body sought restitution of funds paid pursuant to unlawful contract for incomplete works – whether parties are “in pari delicto” – public body entitled to recover funds


COSTS – appeal from indemnity costs order – where National Court awarded costs on an indemnity basis – where costs ordered differentiated between respondents – where National Court did not explain reasons justifying award of indemnity costs or differentiation between respondents – where proceeding brought by unsuccessful party grounded in a mistaken understanding of law did not justify an award of indemnity costs – indemnity costs order set aside


Facts:


On an unspecified date in 2013, Red Coco Properties Limited (Red Coco) entered into a contract with various public bodies and the Goroka Secondary School (School) for the construction of additional school buildings, toilets and staff accommodation at the School (Contract). The Contract was subject to the terms of the Public Finance (Management) Act 1995, which materially required public tender and approval by the relevant Minister. These provisions were not complied with. The Contract was accordingly unlawful.


The material terms of the Contract included:


The parties did not conduct themselves in accordance with the terms of the Contract. Between 12 March and 16 December 2014, K3,799,344 had been paid to Red Coco by various public bodies connected with the School. Despite all but K40,490 of the contract price being paid, Red Coco had not completed all of the buildings stipulated in the Contract. Of the buildings that had been completed – and certificates of practical completion issued – Red Coco had retained the keys such that the School was unable to use them.

In March 2019, a further K1,000,000 was paid to Red Coco by the School, purportedly pursuant to a renegotiation of the Contract.

Red Coco commenced proceedings in the National Court alleging that certain amounts remained unpaid to it under the Contract. The respondents brought a crossclaim against Red Coco, seeking to recoup amounts said to have been overpaid to Red Coco. The National Court dismissed Red Coco’s claim and ordered Red Coco repay the respondent’s K1,598,460 purportedly paid pursuant to the March 2019 renegotiation and K833,605 of overpayments under the Contract.

Red Coco appealed from that judgment.


Held:


  1. At common law, a “lump sum” contract means a contract in which payment will only become due upon completion. Parties to a contract may evince an intention to displace the common law meaning. Where parties include contractual stipulations for progress claims and payments, the parties will be taken to have intended that the contract price will be fixed, albeit paid by instalments: PDC Constructions (NG) Pty Ltd v Commonwealth of Australia [1969] PGSC 66 referred to.
  2. Where a contract price is fixed, and subject to the contrary intention being evinced by the parties, the supplier will bear the risk for correctly pricing the work.
  3. Where the parties to an unlawful contract are not equally at fault, then the parties are not in pari delicto and as such the innocent party is entitled to recover funds mistakenly paid. The fact that the contract had been rendered unenforceable as a result of illegality does not deprive any right to advance such a claim: Putput Logging v Ambalis [1992] PNGLR 159; N1094 and Equuscorp Pty Ltd v Haxton (2012) 246 CLR 498 applied.
  4. When exercising discretion to award costs on an indemnity basis, it is incumbent on the Court to provide reasons for departing from the usual, party and party basis under Order 22, rule 23 of the National Court 1983.

Cases Cited:


Papua New Guinea Cases:
PDC Constructions (NG) Pty Ltd v Commonwealth of Australia [1969] PGSC 66
Putput Logging v Ambalis [1992] PNGLR 159; N1094
Teine v University of Goroka [2019] PGSC 108; SC1881


Overseas Cases
Equuscorp Pty Ltd v Haxton (2012) 246 CLR 498


Legislation Cited:


Papua New Guinea Legislation
Fairness of Transactions Act 1993
National Court Rules 1983
Public Finance (Management) Act 1995


Counsel:
Mr. S Gor, for the Appellant
Mr. R Yombou, for the First, Third, Fourth and Fifth Respondents
Mr. B Nahupa, for the Second Respondent


23rd February, 2023


  1. BY THE COURT: These proceedings arise out of a contract (the Contract) made in 2013 for the construction of additional school buildings, toilets and staff accommodation at Goroka Secondary School. On the face of the Contract, these buildings were supposed to be completed by the end of 2013. Approaching a decade later and after the payment of millions of kina to the appellant building contractor, Red Coco Properties Limited (Red Coco), the buildings have not been fully completed. Moreover, in relation to those which have been completed, Red Coco has refused to hand over the keys to any of the respondents. Instead, Red Coco claims that it is still owed monies by the respondents (or some of them).
  2. In pursuit of monies allegedly owed, Red Coco instituted proceedings against the respondents in the National Court at Goroka. There came to be a crossclaim against Red Coco in those proceedings to recover an alleged overpayment. The proceedings went to trial in the National Court there.
  3. Following the trial, the National Court came to make the following orders:
    1. Judgement for the Goroka Secondary School (the Fifth Respondent and the Firth Defendant/Third Cross-Plaintiff below) [sic], with Red Coco (the appellant and Plaintiff/Cross-Defendant below) to pay the Goroka Secondary School K2,432,065, that judgement sum being immediately due and payable.
    2. The order of the Court made 24 September 2020 addressed to Westpac Bank PNG Ltd restraining the Bank from allowing the funds in the account of the Goroka Secondary School to be reduced to K600,000 or some lesser amount, is dissolved, the Goroka Secondary School being at liberty to deal with the account.
    3. The Bank of South Pacific Ltd and its servants and agents are restrained from allowing the funds of the plaintiff whether described as Red Coco Properties Limited or Redcoco Builders and whether in an account numbered [omitted] or another account, to be reduced to or to an amount less than K1,598,460. This order may be served on Bank of South Pacific Ltd by delivery to a branch manager of the Bank of South Pacific Ltd or by email to a legal officer of the Bank of South Pacific Ltd.
    4. Order numbered 3 shall lapse by effluxion of time after 45 days of today should there be no further order.
    5. The directors of the plaintiff and servants and agents of the plaintiff who have authority to operate the bank accounts noted in Order numbered 3 are restrained from withdrawing and dissipating funds from those accounts such as may cause those accounts to be reduced to or to an amount less than K1,598,460.
    6. Order numbered 5 shall lapse by effluxion of time after 45 days of today should there be no further order.
    7. The Plaintiff is to further pay the Goroka Secondary School pre-judgement interest on the award of K180,317.
    8. From judgement, interest is payable on the K2,432,065 at the rate of 8% yearly in accordance with the Judicial Proceedings (Interest on Debt on and Damages) Act. No interest is payable on interest.
    9. The plaintiff to pay the costs of the First, Third and Fifth Defendants (the First, Third and Fifth Respondents) on an indemnity basis to be taxed if not agreed and on the basis that these three defendants are considered one party for costing.
    10. The plaintiff to pay the costs of the Second and Sixth Defendants on an indemnity basis at 2/3 rate and to be taxed if not agreed and on the basis that these two defendants are considered one party for costing.
    11. No costs to the State.
    12. Time abridged to the date of settlement by the Registrar, forthwith.
  4. Red Coco now seeks to challenge each of the above orders, save orders 11 and 12, in what have become consolidated appeals. Including grounds concerning findings of fact permitted by leave to be raised, the grounds of appeal as pleaded are as follows:
    1. The trial Judge erred in mixed fact and law in finding that the Contract of 13 March 2013 between the First, Second and Fifth Respondents (of the one part) and the Appellant (of the other part) (the Contract) was an illegal contract for failing to comply with the public tender process under sections 59 and 61 of the Public Finances (Management) Act 1995 when the unrebutted evidence from the parties was that there was substantial compliance with the tender process envisioned by section 59 of the Public Finances (Management) Act 1995.
    2. The trial Judge erred in mixed fact and law in finding that the Goroka District Administration (GDA), represented by the First and Second Respondents, did not breach clauses 10.2 (progress claims), 10.4 (progress payments) and 10.5 (failure to issue or pay progress certificates) of the Contract when the Appellant’s unrebutted evidence showed clear breaches of these clauses by the GDA.
    3. The trial Judge erred in mixed fact and law in finding that the amount of K699,344 paid by the School to the Appellant was for the project under

the Contract and not for the construction of a staff duplex in circumstances where:

  1. by its own letter dated 13 May 2014 to the GDA the School confirmed that it paid K699,344 of its own funds to the Appellant. The School did not want a refund of this money from the Appellant. Instead, in consideration of this money the School and the Appellant agreed that the Appellant will construct the staff duplex for the School; and
  2. by December 2014 the Appellant constructed and completed the staff duplex which is ready for occupancy and use.
  1. The trial Judge erred in mixed fact and law in finding that the Appellant benefitted from the funding of K336,000 received from NGCB in July 2016 when the unrebutted evidence of the Appellant was that the funding from NGCB was used to improve the incomplete quadruplex.
  2. The trial Judge erred in mixed fact and law in finding that the Certificates of Completion issued by the Eastern Highlands Provincial Building Board for three of the buildings built by the Appellant were incorrect.
  3. The trial Judge erred in mixed fact and law by not assessing damages in favour of the Appellant after finding that as of December 2013 the GDA breached the Contract in failing to pay the Appellant the full contracted sum of K3,839,833.80.
  4. The trial Judge correctly found that there was no duress or undue influence exerted by Hon. Henry Ame, MP on the representatives of the GDA and Goroka Secondary School (the School) when the parties, that is, the GDA and the School (of the one part) and the Appellant (of the other part) entered into the Agreement of 17 January 2019 (the Agreement), but fell into error of law, and or of mixed fact and law, in finding that the Agreement was flawed and unenforceable.
  5. The trial Judge erred in mixed fact and law in finding that the Appellant should repay the School K1,598,460 pursuant to the Agreement when the undisputed evidence of the parties showed that the:
    1. amount stated in the Agreement is K1,598,973.38 and not K1,598,460; and
    2. Appellant only received K1 million from the School and not the whole amount of K1,598,973.38
  6. The trial Judge erred in mixed fact and law by ordering the Appellant to pay pre-judgement interest at 8% per annum on the following amounts:

a. K1,598,460; and b K218,505

  1. The trial Judge erred in mixed fact and law in ordering the Appellant to pay the Respondents’ costs on an indemnity basis.
  2. Further or alternatively to ground 3, the trial Judge erred in law, and or mixed fact and law in finding that the Appellant is liable to repay the School the amount of K2,432,065 with interest and cost when applying the principles of in pari delicto as enunciated by the Supreme Court in Gago Teine & Anor v. The University of Goroka [2019] SC1881.
  3. The trial Judge erred in fact in finding that the School alone, excluding the GDA, paid K3,799,344 to the Appellant by December 2014.

The evidence of parties showed, from 11 March 2013 to 5 September 2013 the School made five payments to the Appellant totalling K999,344

From 2 October 2013 to 5 November 2013 the GDA made seven payments to the Appellant totalling K2,100,000.

From 12 March 2014 to 16 December 2014 the GDA made five payments to the Appellant totalling K700,000.

  1. The trial Judge erred in fact in finding that the School paid K999,344 of its own funds to the Appellant when the School’s own evidence showed clearly that the School only paid K699,344 of its own funds to the Appellant.
  2. These grounds will now be considered in turn.

The Public Finance (Management) Act 1995

  1. Consideration of this ground first requires that s 59 and s 61 of the Public

Finance (Management) Act 1995 (PFM Act), as they stood in 2013, be set out: 59. CONTRACTS FOR WORKS AND SERVICES.

(1) Subject to Subsection (2), tenders shall be publicly invited and contracts taken by a public body to which this Act applies for all works, supplies

and services the estimated cost of which exceeds such sum as is specified in its constituent law or declared by the Minister.

(2) Subsection (1) does not apply to any works, supplies and services–

61. APPROVAL REQUIRED FOR CERTAIN CONTRACTS.

(1) The provisions of this section apply to and in respect of all public bodies notwithstanding any provision to the contrary in any other law and notwithstanding and without regard to any exceptions, limitations, conditions, additions or modifications contained in any other law.
(2) Subject to Subsection (3), a public body shall not, except with the approval of the Minister, enter into a contract involving the payment or receipt of an amount, or of property to a value, (or both) exceeding–
(3) The provisions of Subsection (2) do not apply to a contract relating to investment by a public body (including a subsidiary corporation) the subject of a declaration under Section 57(3).
  1. None of the respondents pleaded in their defence that the Contract was illegal by virtue of non-compliance with the PFM Act. However, the learned primary judge took the view that the question of whether the PFM Act applied so as to render the Contract illegal was not one which could be ignored. Red Coco does not suggest in any of its grounds of appeal that, by so doing, his Honour visited any denial of procedural fairness on it. Neither does it suggest that the PFM Act was inapplicable to the Contract. Rather, its contention is that there was substantial compliance with the PFM Act.
  2. In entering into the Contract, Red Coco contracted with public bodies for the purposes of the PFM Act. The amount to be paid under the Contract for the contracted works and related goods (furniture) exceeded the amounts specified in or for the purposes of s 59 and s 61 of the PFM Act. Contrary to s 59, the tender was closed, not public. Contrary to s 61, there was never any Ministerial approval. The evident purposes of the respective sections were, on the one part, both to secure value for public money and diminish potential for “crony capitalism” by open, competitive tenders and, on the other part, to ensure Ministerial scrutiny of major public projects. In neither regard do the purposes of these sections of the PFM Act admit of substantial compliance. To so construe them would be subversive of those purposes. The Contract was, therefore, an illegal contract. The primary judge was correct to so conclude.
  3. That conclusion was an essential pre-condition for his Honour’s consideration of the operation of the in pari delicto doctrine in the circumstances of the present case. We address his Honour’s consideration later in these reasons for judgement.

Appeal grounds 2, 3, 6, 12 and 13

  1. Grounds 2, 3, 6, 12 and 13 may conveniently be considered together. Consideration of them is, necessarily, subject to the over-arching conclusion that the Contract was an illegal contract.
  2. The learned primary judge found that the Contract was entered into in 2013. Like his Honour, we find it difficult to be more specific than that. Nominally, the Contract is dated 13 March 2013. Yet, as his Honour noted, the opening page puts the date as “September (space) April 02, 2013”, while the page before the attestation page states “The contract will commence on 10th March 2013 and will be completed on 10th December 2013”.
  3. What is clear enough is that the tender made by Red Coco and accepted by the respondents was to execute the project works pursuant to a “Lump Sum Contract to be paid progressively according to ‘actual work completed’ and verified by the Project Manager” for the sum of K3,839,833.80, with the terms of the contract more particularly detailed in “General Conditions for Minor Works Contract (1994)” (General Conditions).
  4. Taken in conjunction with the specified date for practical completion, the primary judge construed the contract to require:

“the builder to bring the project to practical completion by 10 December 2013 and then the School will pay the lump sum to the plaintiff. Clause 6.8 provides that the builder will remedy defects not noticed at the time of practical completion. Clause 11, subject to exceptions, states a Certificate of Completion is to be evidence of completion.”

His Honour therefore construed “lump sum” to mean a fixed amount to be paid in full upon the practical completion of the building project (see, in particular, [6] and [38] of his Honour’s reasons for judgement).

  1. Ground 2 challenges this conclusion as to the meaning of “lump sum”, in so doing drawing attention to cls 10.2, 10.4 and 10.5 in the General Conditions. Clauses 10.2 and 10.4 provide for progress claims and progress payments respectively. Clause 10.5 is directed to the consequences of a failure to pay a progress claim on time.
  2. Viewed in the abstract and without reference to the context in which it is used in the Contract, there is some support for the conclusion of the primary judge. In PDC Constructions (NG) Pty Ltd v Commonwealth of Australia [1969] PGSC 66 (PDC Constructions) and with reference to an authoritative text on building and construction law, Frost J (as his Honour then was) stated:

At common law a “lump sum” contract means an entire contract in which the law will not imply a term for any payment prior to completion (Hudson's Building and Engineering Contracts,9th Edition, pages 150151).

Yet, as in that case, the terms of the Contract, indicate that “lump sum” is not being used by the parties in keeping with its common law meaning. The presence of contractual provision for progress claims and payment, cls 10.2, 10.4 and 10.5 of the General Conditions, and the qualification of “lump sum” by “to be paid progressively” make this clear. Instead, the term “lump sum” is being used in the same sense as Frost J found it was used in PDC Constructions:

These words are intended to make plain that no adjustment to the contract price is to be made if the quantities in the Bill should prove to be incorrect. (See Hudson’s Building & Engineering Contracts, 9th Edition, page 150, and the cases cited on pages 203-205).

16. As used in the sense described in PDC Constructions and in the present case, a “lump sum” contract places on the building contractor the responsibility of calculating the project cost, including overheads and its profit. In effect, the building contractor assumes the risk of correctly pricing the project works from the plans. If it transpires that it is possible to complete those works for less than the lump sum specified in the contract, the building contractor’s profit margin increases; if not, it decreases. As used in this sense, a “lump sum” contract may be distinguished from what is termed a “cost-plus” contract, in which the owner/client pays all of the costs, be they fixed, variable or overhead and additional fees and margin to the building contractor.
17. In the sense used in the Contract, there was no necessary inconsistency between the stipulation that it was a “lump sum” contract and provision for progress payments. To this extent therefore, the construction of the Contract adopted by the primary judge was incorrect.


18. This error as to the applicability of the progress claim and payment cls (10.2, 10.4 and 10.5) does not have any consequence, because the parties conducted themselves with an almost sublime disregard to these clauses. Instead, between 11 March 2013 and 15 November 2013, the respondents had, as his Honour found, paid Red Coco instalments totalling K3,099,344. Each of these payments was referable to the Contract. It is irrelevant that some were paid directly by the Goroka Secondary School and some from the Goroka District Treasury. By 10 December 2013, Red Coco had not brought the project works to practical completion.


19. Between 12 March 2014 and 16 December 2014, further instalments totalling K700,000 were paid to Red Coco. Thus, by 16 December 2014, the respondents had paid Red Coco a total of K3,799,344 in respect of the project works. There was a separate project in relation to the construction of a duplex. The trial judge was correct to find that this project was not governed by the Contract and that, on the evidence, none of the instalments paid was referable to this separate project.

20. None of these instalments could be described as progress payments in accordance with cls 10.2 and 10.4 of the Contract. But that does not mean they were not paid to or accepted by Red Coco in respect of the project works. The primary judge was correct to find, on the evidence, that this was the basis upon which each of the instalments was paid to Red Coco.

21. All that was left to pay of the lump sum for which Red Coco undertook to bring the works to practical completion was, as the primary judge correctly found, K40,490. Still by the date of trial, Red Coco had not brought the project works to practical completion.

22. The project works for which the Contract provided were:

  1. a Science laboratory;
  2. a Library and a Computer Laboratory;
  1. male and female toilets;
  1. four separate units each of 3-bedrooms, joined and called “4-1 housing” (for staff accommodation).

23. Of these buildings, (a), (b) and (c) had been built by the time of trial. Red Coco retained the keys to these buildings.

24. On the true meaning of “lump sum”, the balance of K40,490 was only ever payable upon the practical completion of the project works. Red Coco has not to this day brought the project works to practical completion. Even were the Contract not illegal, it would have no entitlement to be paid the balance.
25. Red Coco’s delay in completing the project works was said to be due to materials cost escalations because of exchange rate variations between the PNG Kina and the Australian Dollar and delay by the respondents in making progress payments. As already found, the provision in the Contract for progress claims and payments was just disregarded by the parties with the respondents just choosing to pay, and Red Coco choosing to accept, a series of instalment payments.


26. Further, although the General Conditions did contain “rise and fall” clauses (cls 10.6 and 10.9), which might otherwise have covered changes in materials costs, this was, as the learned primary judge correctly found, expressly excluded by a special condition in the Contract, cl 15. This provided:

SPECIAL CONDITIONS COST ADJUSTMENT

The moneys payable to the Contractor under this Contract are not subject to adjustment for rise and fall in costs notwithstanding Clauses 10.6 and 10.9 of this contract.

27. Clause 15 reinforces the meaning of “lump sum” as used in the Contract. Given that meaning, as reinforced by cl 15, Red Coco assumed the risk of changes in materials costs by entering into the Contract. In the face of cl 15, Red Coco’s assertion of a contractual entitlement to be paid for the increased cost of materials is and was always specious. Yet, overwhelmingly, on the evidence at trial, it was this specious understanding of its contractual bargain which informed Red Coco’s failure to complete the project works and to seek further payments from the respondents.

Ground 5

28. Red Coco’s evidence at trial included three certificates of completion, each dated 15 November 2015, apparently issued by the Provincial Building Board, attesting to the completion of particular items in the project works:

  1. the Science laboratory;
  2. the Library and Computer Laboratory;
  3. the male and female toilets/ablution blocks.

29. It was common ground that the 4-1 housing units had not been completed.


30. The accuracy of these certifications was challenged by the respondents. They relied on the evidence of an architect and building expert, Mr Stearford Taosi Amevo (termed “Mr Stearford by the learned primary judge and likewise for consistency in this judgement).


31. Mr Stearford had inspected the project works for the purpose of preparing his report. That inspection was hampered by a failure by Red Coco to facilitate his access to the interiors by not making the keys available to him or otherwise making an access arrangement. Even so, Mr Stearford was able to look inside and assess the degree of completion, including whether contractually contemplated furniture had been provided. His inspection then became the subject of a report, which the primary judge described as “impressive”. He was cross-examined on that report.


32. As the primary judge accurately recorded, Mr Stearford’s evidence was that he observed from outside the buildings that the following contractually specified fixed and moveable furniture was not in place (amounts are as per the cost estimate for the Contract):

  1. Computer laboratory and Library:
    1. fixed furniture - K32, 620 ii. moveable furniture - K42, 860
  1. Science Laboratory:
    1. fixed furniture value - K44, 900 ii. moveable furniture - K98, 145.

33. In relation to the toilet block, Mr Stearford’s evidence was that the ceiling had not been completed. A photo in evidence, taken by him, confirmed this.

34. At trial, evidence was led for Red Coco from Mr Ted Sansip. Mr Sansip was engaged as Consultant Project Manager on the Goroka Secondary School Project by Red Coco. He compiled the original Bill of Quantities of the Goroka Secondary School Project in 2012. Mr Sansip is the holder of a Diploma of Building. He had worked on various major building and construction projects around the country. Mr Sansip’s evidence was discounted by the primary judge on the basis that it was really a mathematical extrapolation from this original Bill of Quantities. The trial judge was entitled to do this. It was the trial judge who saw and heard the witnesses called. On appeal, we do not have that advantage. In preferring Mr Stearford, the primary judge did not misuse that advantage. Independence from a party in dispute also offers a logical basis for his Honour's preference. There is no doubt he had the expertise to express opinions about the state of completion of all of the project works. His report is indeed comprehensive.

35. Red Coco also led evidence from an architect, Mr Jelif Hevis (termed Mr Jelif by the primary judge and in this judgement). Mr Jelif’s evidence was that the 4-1 housing was about 60% complete at the end of 2014 (and had since been vandalised). On this subject, Mr Stearford’s evidence was that, as at the end of 2014, the 4-1 housing was about 57% complete. As his Honour found, on this subject, those witnesses were in substantial agreement. However, neither of these bodies of evidence went to the accuracy of the certificates of completion.

36. On the basis of his acceptance of Mr Stearford’s evidence, the primary judge was entitled to conclude that the certificates of completion were not accurate.


Appeal Grounds 4, 7, 8 and 9

37. Specious though it was, Red Coco’s claim to be owed further money under the Contract resulted in further payments to it.

38. In July 2016, K336.000 was paid to it by the National Gaming Control Board (NGCB). Red Coco claimed, via ground 4, that this money went to the improvement of the 4-1 housing part of the project works. But Red Coco was already obliged under the Contract to bring the whole of the project works to completion, including the 4-1 housing, for the lump sum price as specified in that contract.

39. The primary judge made no finding that the sum of K336,000 was paid on behalf of the respondents or any one of them by the NGCB. Ultimately, however, the reasons for judgement of the primary judge reveal that that sum does not feature as a component of any amount ordered to be paid by Red Coco by the orders under appeal. Thus, even if ground 4 had merit, it would lead nowhere.

40. Two further sums were paid to Red Coco. In March 2019, Goroka Secondary School paid it K500,000 on 14 March 2019 and a further K500,000 on 29 March 2019. These payments were sourced in a sum of K2,000,000 from the National Department of Education and paid into the School’s bank account following representations by a then local member of parliament, Mr Henry Ame.

41. These two payments were referable to what purported to be a renegotiation of the Contract in January 2019. On 9 January 2019, having earlier received an invoice from Red Coco in the sum of K1,598,460 for what was said to be monies owing to it under the Contract the Goroka Secondary School made an agreement (the renegotiation agreement) with Red Coco which recited, amongst other things, “F. The District Authority is desirous of ensuring that the outstanding project invoice is settled and the keys to the respective buildings handed over the school. G. The school is not able to raise payment for the equivalent of the monies owed to the builder as the school account is still closed therefore the aforesaid parties agree to settle the payment as follows:”, and then provided:

  1. The builder completed the project and rendered invoice for KI,598, 460 which has not been settled, consequently the builder has not handed over the keys to the completed buildings.
  2. Through Mr Ame K2,000,000 was available to pay that sum.
  3. The School undertakes to pay the K1,598,460 by 8 February 2019.

42. On the true construction of the Contract, as detailed above, none of the respondents, including the school, owed Red Coco anything at that stage. Red Coco was not entitled to any further payment unless and until it completed the entire project (by the stipulated time) and then only to the balance of the contract price.

43. What follows from this is that Red Coco could offer no consideration in relation to the so-called renegotiation of the contract. The learned primary judge observed (at para. 100) of this renegotiation”

The renegotiated agreement is fundamentally flawed as it was without consideration for the contract to be renegotiated where there was no benefit to the School but enrichment for the plaintiff. The payment of money demanded in the renegotiated agreement was not fair nor just nor did the School's representatives obtain competent independent advice.

We respectfully agree with this observation.

44. The learned primary judge noted that, although reference was made in submissions made on behalf of the present respondents to the Fairness of Transactions Act, that statute was not referred to in their pleadings. Having noted this, his Honour stated that this Act was not applicable for reasons given later in his reasons for judgement. Unfortunately, and with respect, those reasons are not later given.

45. It may be that his Honour had in mind the exclusion by paragraph (e) from the definition of “transaction” in s 3 of the Fairness of Transactions Act of “a transaction that is renegotiated and its terms are substantially altered after three years of the date of the original transaction”. Here, the original transaction, that is the contract, was made in 2013. The purported renegotiation occurred more than three years later, in January 2019. On the facts, the exclusion found in this definition was engaged. Thus, although his Honour did not specify a reason for his conclusion that the Fairness of Transactions Act 1993 (Fairness in Transactions Act) was not applicable, that conclusion was, for the reason just given, correct. We add that, had that Act been applicable, it would, having regard to the concept of “fairness” as described in s 4 of that Act, have been very difficult indeed to characterise the purported renegotiation as “fair”. Put bluntly, and to adopt descriptions offered by the primary judge, Red Coco created a myth of a cost blow out entitling it to additional payment.

46. Notwithstanding his conclusion that the Fairness of Transactions Act was not applicable, his Honour nonetheless found that Red Coco was obliged to refund to the respondents the sum of K1,598,460 paid to Red Coco following the “renegotiation”.

47. The reasoning which led the learned primary judge to his conclusion that this sum was recoverable commenced with reference to Teine v University of Goroka [2019] PGSC 108; SC1881 (Teine), in which this Court addressed the circumstances in which monies paid under an illegal contract might be recoverable. One relevant consideration, so the court found, was whether the parties to the contract were in pari delicto (a situation in which the parties are equally at fault). If the parties are equally at fault, monies paid under an illegal contract will not be recoverable.

48. The learned primary judge noted that, in Teine, this Court had referred with approval to the following observation made by Sheehan J in Putput Logging v Ambalis [1992] PNGLR 159; N1094:

“In pari delicto may be translated as describing a situation where the parties are equally at fault. If that is the case, the parties are stuck with their agreement and no rights or obligations can be enforced. But where they are not equally at fault (where there may have been duress, a mistake of fact, or where the duty of observing the law in the field where the contract arose is placed on one rather than the other), that is, where the law is plainly intended for the protection of a class of persons, parties are not in pari delicto and monies can be recovered.”

49. It is tolerably clear from his Honour’s reasons for judgement that his conclusion was that Red Coco and the respondents were not, in relation to the “renegotiation”, in pari delicto. That conclusion was, having regard to what we have stated above concerning that event, well open on the evidence. Indeed, it was unremarkable.

50. That being so, his Honour concluded that the unfairness of the payment of the sum of K1,598,460 paid to Red Coco was such that it was recoverable. His Honour did not, with respect, explore any further than beyond reference to the two cases just noted, the jurisprudential basis upon which that sum was recoverable. But it is to be remembered that this was a case heard and determined at Goroka in the Eastern Highlands, where the library facilities available to a trial judge are limited indeed. But, in the circumstances, the respondents had a restitutionary claim against Red Coco for money had and received by it. Further, the illegality that rendered the contract unenforceable did not deprive them of their right to advance such a claim against Red Coco; contrast Equuscorp Pty Ltd v Haxton (2012) 246 CLR 498. The purposes of the PFM Act, referred to above, were protective of the interests of the State (and those representing the State or a subordinate body politic) in the proper application of public funds. Here, the countenance of a restitutionary claim by the respondents notwithstanding illegality of contract is completely harmonious with the purposes of the PFM Act.

51. The conclusion of the primary judge that the respondents were entitled to recover the sum of K1,598,460 paid to Red Coco was correct.

52. Based on his preference for Mr Stearford’s evidence, the primary judge also found that the respondents were entitled to recover the following further sums from Red Coco:

Value of furniture
K218,525
Value of work to complete on the 4-1 housing
K655,570
Sub-total
K874,095
Less outstanding at 2014
K40,490
Total
K833,605

53. There is no cross-appeal by the respondents that the primary judge erred in this assessment by allowing Red Coco the benefit of the sum of K40,490, which was only payable to it in the event that it completed the whole of the project works. On the findings made by the primary judge, which were open on the evidence, Red Coco never completed the whole of the project works, only 60% thereof. The cost of completing the value of the works was, in light of the evidence preferred by the primary judge, K655,570, with the cost of furniture which should have been supplied but was not K218,525. Red Coco never had any entitlement to the balance of the contract lump sum, because it never completed the project works. It was not entitled to the credit allowed by the primary judge. However, as there was no cross-appeal, it would be procedurally unfair to do other than act on the basis of the credit allowed to it by the primary judge.

54. In the circumstances, Red Coco has not shown that these additional items in the total sum of K833, 605 allowed by the primary judge by way of damages for breach of contract were not allowable.

55. The awarding of interest on the sums found to be owing by Red Coco was entirely orthodox.

Ground 10

56. Ground 10 challenges the awarding of costs against Red Coco on an indemnity basis. The primary judge noted that such a claim for costs had been made by the respondents. However, the primary judge did not detail why it was that he had decided that the circumstances of the case were such that he should depart from the usual position that costs are awarded on a party and party basis. With respect, it was incumbent upon his Honour to provide such detail in his reasons for judgement. The awarding of costs calls for the exercise of a judicial discretion. The usual way in which that discretion is exercised is that costs follow the event (Order 22, rule 11, National Court Rules 1983) but are taxed on a party and party basis unless otherwise ordered (Order 22, rule 24, National Court Rules 1983).

57. The conduct of Red Coco, in asserting a claim based on a mistaken understanding in law of the contract and of its “renegotiation” did not, in itself, provide a basis for making other than the usual order as to costs.

58. The costs orders made by the primary judge also differentiated as between the present respondents. Once again, the primary judge did not, as with respect he should have, explain that differentiation. However, it seems, inferentially, to have reflected his assessment in relation to issues raised by particular defendants (or groups thereof) and the degree of forensic success or failure. The differentiation operated in favour of Red Coco. We see no reason to disturb that.

59. Ground 10 should therefore, to the extent noted, be upheld.

Disposition

60. What follows from these reasons for judgement is that the appeal should be allowed in part and Orders 9 and 10 made by the National Court should be set aside. In lieu thereof, it should be ordered:

  1. The plaintiff (the appellant) to pay the costs of the First, Third and Fifth Defendants (the First, Third and Fifth Respondents) on a party and party basis to be taxed if not agreed and on the basis that these three defendants are considered one party for costing.
  2. The plaintiff to pay the costs of the Second and Sixth Defendants on a party and party basis at 2/3 rate and to be taxed if not agreed and on the basis that these two defendants are considered one party for costing.

61. Save as aforesaid, the appeal should be dismissed.

62. The point on which Red Coco has succeeded on the appeal is a straightforward one. It has otherwise comprehensively failed. The issues on which it failed were, as these reasons for judgement reveal, the more complicated and consuming of time both in oral submissions and in related written submissions. It would, of course, be possible to allow some percentage discount in respect of costs awarded against Red Coco as on one event it did succeed. The percentage justly so allowed would be so minor (less than 1%) as to be virtually negligible in end result after taxation. In the circumstances, we consider that no discount is warranted.

63. The appropriate further order is therefore that Red Coco pay the respondents’ costs of and incidental to the appeal on a party and party basis, to be taxed if not agreed.

Orders

  1. The appeal be allowed in part.
  2. Orders 9 and 10 made by the National Court in proceeding WS No. 656 of 2020 be set aside and in lieu thereof it be ordered:
    1. The plaintiff (the appellant) to pay the costs of the First, Third and Fifth Defendants (the First, Third and Fifth Respondents) on a party and party basis to be taxed if not agreed and on the basis that these three defendants are considered one party for costing.
    2. The plaintiff to pay the costs of the Second and Sixth Defendants on a party and party basis at 2/3 rate and to be taxed if not agreed and on the basis that these two defendants are considered one party for costing.
  3. Save for the aforesaid, the appeal be dismissed.
  4. The appellant pay the respondents’ costs of and incidental to the appeal on a party and party basis, to be taxed if not agreed.

_________________________________________________________________
Tamutai Lawyers: Lawyers for the Appellants
O’Briens Lawyers: Lawyers for the Respondents



PacLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback
URL: http://www.paclii.org/pg/cases/PGSC/2023/7.html